Skip to content
Compost Kings Compost Facility, Colebrook
Waste and recycling · Colebrook · Tasmania
- To a 132 kV line
- 24 km
Overview
The proposal is for a resource recovery works (composting facility) with a maximum production capacity of 10,000 tonnes per annum, located on a rural property at Colebrook.
- Location
- Colebrook (locality centre; the EPA names the locality, not the site), Tasmania-42.5090, 147.3785
- Value
- Not published
- Approving authority
- Board of the EPA Tasmania
- Distance to the grid
- 24 km to a 220 kV line. 35 km to Lindisfarne substation (220 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- Planning
- AssessmentLodged 26 Oct 2020
- ApprovedNow
- Construction
- Operating
EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.
- EPA assessment, Somerton, Lovely Banks Road, Colebrook Tasmania 7027 (Class 2B)Tasmania · Board of the EPA Tasmania26 Oct 2020 → 28 Nov 20255 years 1 monthAssessment completed↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each contains© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the mapSite constraints
Site constraints
Checking national and TAS maps…
Nearby
- Stonehenge Quarry Increase in Production, TunnackApproved8 km
- Knaw Quarry, DysartApproved20 km
- Dysart Quarry, Expansion of Operational Area, DysartIn assessment20 km
- Oatlands Fish Waste Treatment Facility, 6820 Midlands Highway, OatlandsApproved23 km
- Fishs Quarry Production Increase, OatlandsApproved23 km
- Logie Farm Quarry, OrieltonApproved25 km
Sources
- EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Completed, 2025-11-28. Retrieved 25 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.