Dysart Quarry, Expansion of Operational Area, Dysart
Road · Dysart · Tasmania
- To a 132 kV line
- 4 km
Overview
E A & M A Downward are proposing to expand their existing operations at the Dysart Quarry, located off the Midlands Highway, approximately 10 kilometres northwest of Dysart. The proposal involves a small expansion to the area of operation. No changes to the existing production limits of 10,000 cubic metres per year, including the crushing and screening of material, are proposed.
- Location
- Dysart (locality centre; the EPA names the locality, not the site), Tasmania-42.5415, 147.1360
- Value
- Not published
- Approving authority
- Board of the EPA Tasmania
- Distance to the grid
- 4 km to a 220 kV line. 35 km to Chapel Street substation (220 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- Planning
- AssessmentNowLodged 21 Nov 2025
- Approved
- Construction
- Operating
EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.
- EPA assessment, Dysart Quarry (Class 2A)Tasmania · Board of the EPA Tasmania21 Nov 2025 → pending1 year so farIn assessment↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each containsSite constraints
Site constraints
This project runs along a route but is mapped at one point on it, so the screen covers that point only.
Nearby
- Knaw Quarry, DysartApproved0.0 km
- Hydrogen Hub, BrightonIn assessment19 km
- Compost Kings Compost Facility, ColebrookApproved20 km
- Metal Recycling Facility, BridgewaterApproved21 km
- Tyre Recycling Facility Upgrade, BridgewaterApproved21 km
- Boral Bridgewater Quarry, Material Recycling Facility, BridgewaterIn assessment21 km
Sources
- EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Commenced. Retrieved 25 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Spotted an error? Tell us.
Get every change to road projects in TAS, and the firms you follow, in the Monday briefing.