Meander Shale Quarry, Meander

Quarries and extractive · Meander · Tasmania

To a 132 kV line
18 km

Overview

The proposal is to intensify extraction and processing activities at the Meander Shale Quarry from 20,000 to 30,000 cubic metres per year.

Location
Meander (locality centre; the EPA names the locality, not the site), Tasmania-41.6680, 146.5650
Value
Not published
Approving authority
Board of the EPA Tasmania
Distance to the grid
18 km to a 220 kV line. 25 km to Fisher substation (220 kV).Straight line to operational lines and substations of 132 kV or more.

Approval progress

2 approvals on record
  1. Planning
  2. AssessmentLodged 8 Dec 2021
  3. ApprovedNow
  • EPA assessment, Meander Shale Quarry (Class 2A)Tasmania · Board of the EPA Tasmania
    8 Dec 2021 → 7 Oct 20229 months
    Assessment completed↗
  • EPA assessment, Meander Shale Quarry (Class 2A)Tasmania · Board of the EPA Tasmania
    7 Jan 2025 → 22 Dec 202511 months
    Assessment completed↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and TAS maps…
  1. Kryden Quarry Intensification, Meander RoadApproved0.0 km
  2. Deloraine Landfill, Tip Road, DeloraineApproved18 km
  3. Kelly Quarry, Scotts Road, Mole CreekIn assessment22 km
  4. Mole Creek Limestone Quarry Production Increase, Mole CreekIn assessment22 km
  5. Porters Bridge Road Quarry, ExtonApproved23 km
  6. Exton Quarry Capacity Increase, Porters Bridge Road, ExtonApproved23 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Completed, 2025-12-22. Retrieved 25 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Spotted an error? Tell us.