Henty Gold Mine ROM Extension, Zeehan
Waste and recycling · Zeehan · Tasmania
- To a 132 kV line
- 18 km
Overview
The proposal is to increase the footprint by 2.3ha of the existing Run of Mine (ROM) pad at the Henty Gold Mine, 23km north of Queenstown. Henty Gold Mine is an underground mine that produces Gold Doré bars, utilising a Carbon in Leach process to extract gold from mined ore. Ore is extracted from within the mine then transported to the ROM pad, where it is crushed and fed into the mill for processing. The purpose of the ROM extension is to allow for more open area for stockpiling different materials, which includes unprocessed ore, PAF waste rock and NAF waste rock.
- Location
- Zeehan (locality centre; the EPA names the locality, not the site), Tasmania-41.8825, 145.3415
- Value
- Not published
- Approving authority
- Board of the EPA Tasmania
- Distance to the grid
- 18 km to a 220 kV line. 23 km to Farrell substation (220 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- Planning
- AssessmentLodged 20 Aug 2024
- ApprovedNow
- Construction
- Operating
EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.
- EPA assessment, Henty Gold Mine (Class 2B)Tasmania · Board of the EPA Tasmania20 Aug 2024 → 21 Oct 20251 year 2 monthsAssessment completed↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each containsSite constraints
Site constraints
Nearby
- Newton Pond Leach Residual Storage Facility Expansion, Henty Gold MineIn assessment0.0 km
- Zeehan Zinc Project Stage 2, Tasmanian Smelters Site, ZeehanApproved0.0 km
- Avebury Nickel Mine Waste Rock Sorting Facility, ZeehanIn assessment0.0 km
- Tenth Legion Mine Western TasmaniaIn planning5 km
- Renison Tailings Retreatment Project (Rentails Project)In assessment10 km
- Non-Acid Forming Aggregate Storage Facility, Renison BellApproved13 km
Sources
- EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Completed, 2025-10-21. Retrieved 25 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.