How often NSW major project consents are modified

Who this is forAnyone who keeps a compliance register against a NSW State significant consent, and anyone who has found evidence filed against a condition number that no longer exists.
A consent is not a fixed document. Projects change design, staging, hours, haul routes and operators, and each change of substance is made by modifying the consent. We looked at the modification record of every approved NSW State significant project on the claused. Pipeline to see how common that is. The short answer: more common than not.
Six in ten approved projects have been modified
Of 2,866 approved State significant projects in NSW, 1,749 have been modified at least once. Among those, the median is two modifications. A long tail runs well beyond that: 388 projects have been modified five times or more, 84 ten times or more, and one has been modified 35 times.
Show the data
| Modifications | Projects | Share |
|---|---|---|
| Never modified | 1,117 | 39% |
| 1 or 2 times | 989 | 35% |
| 3 or 4 times | 372 | 13% |
| 5 to 9 times | 304 | 11% |
| 10 or more | 84 | 3% |
The flow is steady. In the 90 days to 22 November 2026 the portal recorded 210 modifications across NSW State significant projects, more than two every day.
Mines are modified most
Mining projects are the most likely to have been modified, at 76%, and the most likely to have been modified many times: 91 of 316 approved mines, or 29%, have five or more modifications. A mine consent often runs for decades and changes as the resource, the mine plan and the market change.
Show the data
| Sector | Approved projects | Modified | Share modified | Five or more |
|---|---|---|---|---|
| Mining | 316 | 241 | 76% | 91 |
| Health and education | 367 | 257 | 70% | 38 |
| Industrial | 365 | 229 | 63% | 54 |
| Transport | 390 | 238 | 61% | 44 |
| Energy | 243 | 147 | 60% | 10 |
| Residential and commercial | 920 | 493 | 54% | 121 |
| Water | 47 | 24 | 51% | 2 |
Health and education projects are modified often, 70% of them, but rarely many times: only 38 have five or more. School and hospital consents tend to be adjusted once or twice as the design is finalised and then built. Energy projects sit at the average for being modified at all, but only 10 of 243 have five or more modifications.
Why a modification is a compliance event
A modification can add a condition, delete one, change its wording or renumber the conditions around it. Where the department publishes a consolidated consent after the modification, the numbering in that version is what the next audit will use. Evidence filed against "condition C14" before the change may now belong to C16, or to a condition that no longer exists.
Most registers are kept by hand, and a register kept by hand drifts from the consent it describes at every modification. A project modified five times has five points where the register, the evidence and the approval can fall out of step. Since 21 March 2026, a modification with no environmental impact is meant to be decided within 14 days and cannot be refused once that time has passed, so some changes now arrive faster than they used to.
What to do when a modification lands
- Get the instrument of modification and the consolidated consent. Work from the consolidated version where one is published, and keep the instrument that explains what changed.
- Compare condition by condition. Mark each condition as unchanged, reworded, new, deleted or renumbered.
- Move the evidence with the obligation. Evidence follows the requirement, not the number. Record the old and new numbers side by side.
- Check the plans. A changed condition can require a management plan to be revised and approved again before the changed work starts.
- Tell the people doing the work. A changed hour, limit or hold point means nothing until site knows.
The full process is in a modification was approved: what changes in your register.
Frequently asked questions
How common are modifications to NSW major project consents?
Of 2,866 approved NSW State significant projects on the claused. Pipeline, 1,749 or 61% have been modified at least once. 760 have been modified three times or more and 84 ten times or more. The portal recorded 210 modifications in the 90 days to 22 November 2026.
Which projects are modified most?
Mines. 76% of approved mining projects have been modified, and 29% five times or more. Mine consents often run for decades and change with the mine plan.
Why does a modification matter for compliance?
A modification can add, delete, reword or renumber conditions. Evidence filed against an old condition number may belong to a different condition afterwards, and changed conditions can require management plans to be revised before the changed work starts.
Last reviewed 22 November 2026. General information, not legal advice. The conditions that bind a project are the ones written in its own instruments.