A modification was approved: what changes in your register

Jake, FounderPublished 22 November 20267 min read
A silt fence marked with its chainage at the foot of a grassed batter

Who this is forAnyone who maintains a compliance register for a NSW project whose consent has just been modified, or is about to be.

Six in ten approved NSW State significant projects have been modified at least once, as we found in how often NSW consents are modified. Each modification is a small re-issue of the consent. The register, the plans, the site procedures and the evidence all have to follow it, and the longer that takes the further they drift.

How NSW consents are modified

Development consents, including State significant development consents, are modified under section 4.55 of the Environmental Planning and Assessment Act 1979, or section 4.56 for consents granted by the Land and Environment Court. The Planning System Reforms Act 2025 changed the smallest category from 21 March 2026, for applications lodged from that date. State significant infrastructure approvals are modified under a separate provision, section 5.25 of Part 5, so the section 4.55 pathways below do not apply to them. The register routine later in this guide does.

PathwayWhat it coversWhat changed in 2026
Section 4.55(1)Minor errors, misdescriptions and miscalculations, and now modifications with no environmental impactNo environmental impact moved here from 4.55(1A). To be decided within 14 days, and cannot be refused once that time passes
Section 4.55(1A)Modifications with minimal environmental impact, where the development stays substantially the sameNo longer covers the no impact case
Section 4.55(2)Other modifications where the development stays substantially the sameUnchanged
Section 4.56Consents granted by the CourtUnchanged

The new no environmental impact test is a threshold, not a balance. Any new impact, or a change in where an impact falls or how intense it is, rules a modification out of section 4.55(1). For State significant development the applicant must consult the department through the portal before lodging.

What a modification does to the conditions

A modification is issued as an instrument that lists the changes: conditions inserted, deleted or reworded, and sometimes whole schedules replaced. The department often also publishes a consolidated version of the consent showing it as modified. Each change falls into one of five kinds, and each needs something different in the register.

ChangeAn exampleIn the register
UnchangedC3 reads the same before and afterConfirm and note the modification checked it
RewordedConstruction hours in C5 extended on SaturdaysNew wording, new start date, old wording kept in history
NewC14A requires a new traffic measureNew row, owner, trigger and evidence expectation
DeletedC22 removed with the deleted stageClosed, with the date and the instrument that removed it
RenumberedOld C14 is now C16Old and new numbers side by side, evidence carried across

The examples are illustrative. Renumbering is the one that causes the most trouble later. An auditor working from the consolidated consent will ask for the evidence for C16. If the evidence was filed against C14, someone has to know they are the same obligation.

A five-step routine for the week it lands

  1. Day 1
    Get the instrument and the consolidated consentSave both with the date of the modification. The instrument says what changed. The consolidated consent is what you will be audited against.
  2. Days 1 to 2
    Compare condition by conditionMark every condition unchanged, reworded, new, deleted or renumbered. Do not rely on the instrument's summary alone.
  3. Days 2 to 3
    Move the evidence with the obligationEvidence follows the requirement, not the number. Keep the old and new numbers on the same row.
  4. Days 3 to 4
    Check the plans and approvalsA changed condition can require a management plan to be revised and approved again before the changed work starts, and can affect a licence or other approval.
  5. Day 5
    Brief site and the subcontractorsChanged hours, limits, hold points and notification periods mean nothing until the people doing the work know.

Common mistakes

  • Working from the old PDF. The consent in the site office is still the original. Replace it and mark it superseded.
  • Starting the changed work early. Approval of the modification may not be enough if a plan also has to be revised and approved.
  • Losing the history. An auditor may test a period that spans the modification. The register needs to show which wording applied when.
  • Forgetting the other instruments. A modification to the consent can mean a licence variation or a change to an EPBC approval is also needed.

Frequently asked questions

Are minor modifications deemed approved after 14 days in NSW?

No. Since 21 March 2026, a section 4.55(1) application, which now includes modifications with no environmental impact, is to be decided within 14 days. Under section 4.55A, one not decided in time cannot be refused, but it can still be approved with conditions that relate to the modification.

Which section is used to modify a State significant development consent?

Section 4.55 of the Environmental Planning and Assessment Act 1979, or section 4.56 where the consent was granted by the Land and Environment Court. State significant infrastructure approvals are modified under section 5.25.

What should happen to evidence when conditions are renumbered?

It should follow the obligation, not the number. Record the old and new condition numbers side by side, so evidence filed before the modification can still be shown against the condition as it now reads.

Jake Founder, claused.

claused. is built by a practitioner who ran environmental approvals and compliance on major Australian infrastructure, and got tired of proving compliance out of spreadsheets. About claused.

Last reviewed 22 November 2026. General information, not legal advice. The conditions that bind a project are the ones written in its own instruments.

Keep reading

All 26 guides
Compliance

How often NSW major project consents are modified

61% of approved NSW State significant projects have been modified at least once, and 388 five times or more. The numbers by sector, and why every modification is a change the compliance register has to absorb.

6 min read · 22 Nov 2026

Guides

Conditions of consent register template (Excel)

A free Excel register for consent, EPL, EPBC and CEMP conditions, with twelve worked NSW example rows. What a register must hold, and an honest note on when a spreadsheet is enough.

6 min read · 4 Sep 2026

One email when a guide is published.

New guides and changes to the legislation they cite. About one a fortnight. Unsubscribe at any time.