How many conditions does a NSW consent carry? We counted 429

Jake, FounderPublished 22 November 20266 min read
A silt fence and standing water on a construction site after rain

Who this is forEnvironmental and project managers about to inherit a NSW State significant consent, and anyone pricing the compliance effort a new approval brings with it.

Ask how many conditions a major project consent carries and the honest answer has always been "it depends". We wanted a number. The claused. Pipeline reads the consents published on the NSW Major Projects portal and counts the numbered conditions in each one. As at 22 November 2026 it had counted 429 State significant consents, holding 49,512 conditions between them.

111Conditions in the median consentHalf carry more, half fewer
31Pages in the median consent
55%Carry 100 conditions or more237 of 429
374The most in one consent

The median consent has 111 numbered conditions over 31 pages. The middle half of consents carry between 65 and 160. One in ten carries 187 or more, and the largest we have read carries 374. More than half of all consents, 237 of the 429, cross the 100 mark.

Most NSW State significant consents carry between 50 and 200 conditionsNumber of consents by how many numbered conditions they carry. 429 consents.
Source: claused. Pipeline, NSW Planning Portal records, 22 November 2026.
Show the data
ConditionsConsentsShare
Under 505814%
50 to 9913431%
100 to 1499622%
150 to 19911026%
200 to 249235%
250 or more82%

The shape has two humps rather than one peak. A large group sits between 50 and 99, and a second between 150 and 199. That split is mostly sector, which is where the numbers get interesting.

Schools carry more conditions than wind farms

Group the consents by the kind of project and the spread is wide. Health and education projects, which are mostly new and upgraded schools and hospitals, have the highest median at 158 conditions, and the tightest range: three quarters of them carry 135 or more. Energy projects, mostly wind and solar farms and batteries, have the lowest median at 60.

Health and education consents carry two and a half times the conditions of energy consentsNumbered conditions per consent by sector. Sectors with at least 30 counted consents.
Source: claused. Pipeline, NSW Planning Portal records, 22 November 2026.
Show the data
SectorConsentsLower quarterMedianUpper quarterTop tenth fromMost
Health and education109135158171184238
Residential and commercial9382139185221269
Transport5680102132193289
Industrial398099112127208
Mining416084127159180
Energy6749607287204
Other1948145180251374
Water53296120131139

A count measures how a consent is written, not how hard it is to comply with. School and hospital consents tend to be issued in the department's standard structure, with separate parts for administration, the period before construction, construction, the period before occupation and operation, and a long list of urban construction controls: hours, traffic, noise, dilapidation, tree protection. Energy consents are often shorter on paper but push the detail into management plans. One condition requiring a biodiversity management plan can generate dozens of commitments of its own once that plan is approved.

Residential and commercial consents have the widest spread of any large group. The middle half runs from 82 to 185, which reflects the range of what sits in that group, from build to rent towers to mixed use precincts.

What the count does not include

The consent is only the first instrument. A typical major project also carries an environment protection licence for scheduled activities, an EPBC approval where a matter of national environmental significance is affected, and the approved management plans that the consent itself calls up. Each plan carries its own commitments, inspection frequencies and hold points, and each is enforceable through the condition that requires compliance with it.

So a consent with 111 conditions does not mean a register with 111 rows. Once the licence, any EPBC conditions and the management plan commitments are added, 200 or more obligations on one project is ordinary. Modifications then add, delete and renumber conditions over the life of the project, which we look at in how often NSW consents are modified.

What it means for the register you build

  • Budget for the median, plan for the upper quarter. If your project is a school, a hospital or an urban building, expect 135 to 185 conditions in the consent alone.
  • Count obligations, not condition numbers. A condition with parts (a) to (f) is six things to evidence. Split them in the register so each has an owner and a status.
  • Read the short consents twice. A short energy consent usually means the work lives in the management plans. Break each approved plan into its commitments, as set out in management plan commitments that sit outside the consent.
  • Keep the instrument beside the number. Condition B12 in the consent and condition 12 in the licence are different obligations. A register that drops the instrument name will confuse them.

If you are starting from a blank page, the conditions of consent register template has the columns that hold up at audit.

Frequently asked questions

How many conditions does a typical NSW State significant consent have?

Across 429 consents counted by the claused. Pipeline to 22 November 2026, the median was 111 numbered conditions over 31 pages. The middle half carried between 65 and 160, one in ten carried 187 or more, and the largest carried 374.

Which projects carry the most conditions?

Health and education projects, mostly schools and hospitals, had the highest median at 158 conditions. Residential and commercial followed at 139. Energy projects had the lowest median at 60, although their management plans often carry much of the detail.

Does the count include every obligation?

No. It counts numbered conditions such as A1 or B12. Lettered parts inside a condition, the environment protection licence, any EPBC approval and the commitments in approved management plans all add obligations on top of the count.

Where does the data come from?

The claused. Pipeline reads the consent documents published on the NSW Major Projects portal for approved State significant projects and counts their numbered conditions by machine. Counts with inconsistent numbering, scanned documents and private documents are left out.

Jake Founder, claused.

claused. is built by a practitioner who ran environmental approvals and compliance on major Australian infrastructure, and got tired of proving compliance out of spreadsheets. About claused.

Last reviewed 22 November 2026. General information, not legal advice. The conditions that bind a project are the ones written in its own instruments.

Keep reading

All 26 guides
Compliance

How often NSW major project consents are modified

61% of approved NSW State significant projects have been modified at least once, and 388 five times or more. The numbers by sector, and why every modification is a change the compliance register has to absorb.

6 min read · 22 Nov 2026

Guides

Conditions of consent register template (Excel)

A free Excel register for consent, EPL, EPBC and CEMP conditions, with twelve worked NSW example rows. What a register must hold, and an honest note on when a spreadsheet is enough.

6 min read · 4 Sep 2026

One email when a guide is published.

New guides and changes to the legislation they cite. About one a fortnight. Unsubscribe at any time.