Thomson's Quarry Intensification, Westerway
Quarries and extractive · Westerway · Tasmania
- To a 132 kV line
- 9 km
Overview
Kahuna Pastoral Company is proposing to intensify operations at the existing Thomson's Quarry, located off Styx River Road, approximately 6km from the Gordon River Road, Westerway. The proposal includes an increase in extraction from 5,000 cubic metres to 20,000 cubic metres per annum, and an increase in materials handling (crushing and screening of material) from 1,000 cubic metres to 3,000 cubic metres per annum.
- Location
- Westerway (locality centre; the EPA names the locality, not the site), Tasmania-42.6765, 146.7980
- Value
- Not published
- Approving authority
- Board of the EPA Tasmania
- Distance to the grid
- 9 km to a 220 kV line. 21 km to Cluny substation (220 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- Planning
- AssessmentNowLodged 18 Nov 2025
- Approved
- Construction
- Operating
EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.
- EPA assessment, Thomson's Quarry (Class 2A)Tasmania · Board of the EPA Tasmania18 Nov 2025 → pending1 year so farIn assessment↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each containsSite constraints
Site constraints
Nearby
- Windsors Quarry Extension, HayesApproved17 km
- In-vessel Composting Facility, BoyerApproved27 km
- Coal Transition Project, Boyer Paper Mill, BoyerApproved27 km
- Edgar Dam Strengthening ProjectIn planning29 km
- Lyell Highway – Granton to New NorfolkIn planning · $100m30 km
- Collins Cap Quarry, MolesworthApproved31 km
Sources
- EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Commenced. Retrieved 25 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Spotted an error? Tell us.
Get every change to quarries and extractive projects in TAS, and the firms you follow, in the Monday briefing.