The proposal involves the construction and operation of an in-vessel composting facility, producing up to 14,500 tonnes of compost product per year. The proposal composts within a closed loop system and includes a negative pressure facility that captures and treats (through a biofilter) odour produced from the composting process.

Location
Boyer (locality centre; the EPA names the locality, not the site), Tasmania-42.7680, 147.0995
Value
Not published
Approving authority
Board of the EPA Tasmania
Distance to the grid
2.3 km to a 220 kV line. 15 km to Chapel Street substation (220 kV).Straight line to operational lines and substations of 132 kV or more.

Approval progress

1 approval on record
  1. Planning
  2. AssessmentLodged 13 Sept 2022
  3. ApprovedNow

EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.

  • EPA assessment, Barwicks In-vessel Compising Facility (Class 2B)Tasmania · Board of the EPA Tasmania
    13 Sept 2022 → 30 July 20241 year 10 months
    Assessment completed↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and TAS maps…
  1. Coal Transition Project, Boyer Paper Mill, BoyerApproved0.0 km
  2. Lyell Highway – Granton to New NorfolkIn planning · $100m3 km
  3. Collins Cap Quarry, MolesworthApproved5 km
  4. Windsors Quarry Extension, HayesApproved9 km
  5. New Bridgewater BridgeUnder construction · $786m11 km
  6. Vegetation clearing for residential subdivisionIn planning11 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Completed, 2024-07-30. Retrieved 25 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Spotted an error? Tell us.

Get every change to waste and recycling projects in TAS, and the firms you follow, in the Monday briefing.