This proposal is for the construction and operation of a 20,000 tonnes per annum pre-mix bitumen plant on the land within the mining lease for the Long Hill Quarry, off Dan Road at Elizabeth Town. The application was referred to the EPA Board by Meander Valley Council.
- Location
- Elizabeth Town (locality centre; the EPA names the locality, not the site), Tasmania-41.4280, 146.5645
- Value
- Not published
- Approving authority
- Board of the EPA Tasmania
- Distance to the grid
- 5.5 km to a 220 kV line. 24 km to Sheffield substation (220 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- Planning
- AssessmentNowLodged 1 Nov 2016
- Approved
- Construction
- Operating
EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.
- EPA assessment, Long Hill Quarry, Dan Road, Elizabeth Town 7304 (Class 2A)Tasmania · Board of the EPA Tasmania1 Nov 2016 → pending10 years so farIn assessment↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each contains© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the mapSite constraints
Site constraints
Checking national and TAS maps…
Nearby
- Long Hill Quarry, Elizabeth TownIn assessment0.0 km
- Bass Highway targeted upgrades between Deloraine and DevonportIn planning · $50m10 km
- Parramatta Creek Fish Processing Facility, SassafrasApproved12 km
- Deloraine Landfill, Tip Road, DeloraineApproved13 km
- DL 130 Bauxite Project, Reedy MarshApproved14 km
- Remaining North West Transmission Developments for electricity networkIn assessment17 km
Sources
- EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Commenced. Retrieved 25 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Spotted an error? Tell us.
Get every change to quarries and extractive projects in TAS, and the firms you follow, in the Monday briefing.