Massy Greene Drive Wood Optimisation Hub, South Burnie
Manufacturing · South Burnie · Tasmania
- To a 132 kV line
- 2.2 km
Overview
Pentarch Logisitcs Pty Ltd is proposing modification of its existing Level 2 woodchip mill to include a high-technology wood optimisation hub (sawmill) to divert up to 143,000 cubic meters of its existing eucalypt pulp log feedstock to the wood optimisation hub where logs will be scanned and assessed for suitability of milling. The sawmill will then process the suitable logs, producing up to 60,000 cubic meters of pallet grade lumber for constructing pallets onsite.
- Location
- South Burnie (locality centre; the EPA names the locality, not the site), Tasmania-41.0655, 145.9160
- Value
- Not published
- Approving authority
- Board of the EPA Tasmania
- Distance to the grid
- 2.2 km to a 220 kV line. 2.4 km to Burnie substation (220 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- Planning
- AssessmentLodged 7 June 2023
- ApprovedNow
- Construction
- Operating
EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.
- EPA assessment, Massey Greene Drive Wood Optimisation Hub (Class 2B)Tasmania · Board of the EPA Tasmania7 June 2023 → 11 May 20262 years 11 monthsAssessment completed↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each containsSite constraints
Site constraints
Nearby
- Tyre Processing Facility, BurnieIn assessment1 km
- HIF Tasmania e-Fuels Facility, BurnieIn assessment1 km
- Wivenhoe Oil Recovery Facility, WivenhoeIn assessment1 km
- Tasmanian Freight Rail Revitalisation - Tranche 3 – Port of Burnie Shiploader UpgradeUnder construction · $82m2 km
- Stowport Abattoir Expansion, StowportApproved5 km
- Heybridge Waste Depot Intensification, HeybridgeIn assessment6 km
Sources
- EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Completed, 2026-05-11. Retrieved 25 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.