Fish Processing Facility Upgrade, Dover
Water and wastewater · Dover · Tasmania
- To a 132 kV line
- 53 km
Overview
The proposal is for upgrades to the existing fish processing facility at Dover, to produce up to 50,000 tonnes of product per annum. The proposed upgrade will include an increase in daily effluent discharge up to 720 kL/day from an existing discharge point into Port Esperance, and an upgrade to the wastewater treatment plant.
- Location
- Dover (locality centre; the EPA names the locality, not the site), Tasmania-43.2975, 147.0110
- Value
- Not published
- Approving authority
- Board of the EPA Tasmania
- Distance to the grid
- 53 km to a 220 kV line. 54 km to Chapel Street substation (220 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- Planning
- AssessmentLodged 18 Dec 2020
- ApprovedNow
- Construction
- Operating
EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.
- EPA assessment, Dover Fish Processing Factory, 564 Narrows Road, Dover 7117 (Class 2B)Tasmania · Board of the EPA Tasmania18 Dec 2020 → 12 Mar 20265 years 2 monthsAssessment completed↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each contains© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the mapSite constraints
Site constraints
Checking national and TAS maps…
Nearby
- Stanmore Quarry Capacity Increase, Huon Highway, DoverIn assessment0.0 km
- Maxxis Quarry, Randalls BayIn assessment12 km
- Geeveston Wastewater Treatment Plant, Discharge Relocation, Port HuonApproved17 km
- Whale Point Nursery Intensification and Expansion, Port HuonApproved17 km
- Wooreddy Road Quarry, Bruny IslandIn assessment19 km
- Musketts Road Quarry Expansion, Bruny Island Main Road, AlonnahIn assessment19 km
Sources
- EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Completed, 2026-03-12. Retrieved 25 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.