Aggregate Processing Facility, Long Reach
Transmission · Long Reach · Tasmania
- To a 132 kV line
- 0.7 km
Overview
East Arm Resources Pty Ltd proposes to build and operate an Aggregate Processing Facility (APF) to receive and process into aggregates the rock extracted from the East Arm Road Quarry. The APF includes crushers and screens, conveyors, loaders, hoppers and associated infrastructure (hardstand, powerline, power substation, sediment and drainage systems and ponds, water tank). The proposal also includes a haul road and bridge over Fourteen Mile Creek.
- Location
- Long Reach (locality centre; the EPA names the locality, not the site), Tasmania-41.1660, 146.9560
- Value
- Not published
- Approving authority
- Board of the EPA Tasmania
- Distance to the grid
- 0.7 km to a 220 kV line. 7.2 km to George Town substation (220 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- Planning
- AssessmentNowLodged 22 Apr 2024
- Approved
- Construction
- Operating
EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.
- EPA assessment, East Arm Resources Aggregate Processing Facility (Class 2B)Tasmania · Board of the EPA Tasmania22 Apr 2024 → pending2 years 7 months so farIn assessment↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each containsSite constraints
Site constraints
This project runs along a route but is mapped at one point on it, so the screen covers that point only.
Nearby
- Northern Roads PackageUnder construction · $55m5 km
- East Arm Pine Bark Processing Facility, HillwoodIn assessment6 km
- East Arm Road Quarry, HillwoodApproved6 km
- Artec Woodchip Mill Upgrade, Bell BayApproved8 km
- Aluminium Smelter Bath Waste Recycling Pilot Plant, Bell BayIn assessment8 km
- New Woodchip Processing Facility, Bell BayApproved8 km
Sources
- EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Commenced. Retrieved 25 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Spotted an error? Tell us.
Get every change to transmission projects in TAS, and the firms you follow, in the Monday briefing.