A year of NSW major project approvals: 217 projects, A$63.6bn

Jake, FounderPublished 22 November 20266 min read
A silt fence marked with its chainage at the foot of a grassed batter

Who this is forContractors, consultants and suppliers sizing the NSW major project market, and anyone who wants to know where the next year of construction conditions will come from.

Every approved State significant project is a set of conditions about to land on a contractor. We looked at every NSW State significant development and infrastructure approval recorded on the Major Projects portal in the 12 months to 22 November 2026. There were 217, with a combined capital investment value of A$63.6 billion.

217Projects approved12 months to 22 November 2026
A$63.6bnCapital investment value18 approvals list no value
59%Were housing or commercial129 of 217
72%Of the value in Greater SydneyA$45.6bn

A steady flow, with two big months

Approvals ran at about 18 a month, with no clear seasonal pattern beyond a quiet January. June and September each brought 29 approvals. September was the biggest month by value at A$14.1 billion, driven by four data centres worth A$5.4 billion between them and five energy approvals worth about the same.

June and September each brought 29 approvalsNSW State significant approvals by month, 22 November 2025 to 22 November 2026. The first and last columns are part months.
Source: claused. Pipeline, NSW Planning Portal records, 22 November 2026.
Show the data
MonthApprovalsValue
Nov 255A$3.3bn
Dec24A$8.7bn
Jan6A$0.6bn
Feb14A$3.0bn
Mar15A$4.3bn
Apr21A$6.3bn
May16A$1.0bn
Jun29A$5.7bn
Jul14A$5.2bn
Aug17A$4.6bn
Sep29A$14.1bn
Oct9A$1.1bn
Nov 2618A$5.7bn

Housing leads on numbers, data centres and energy on value

Housing and commercial projects made up 129 of the 217 approvals and A$21.4 billion of the value. Ten data centres were approved, worth A$15.3 billion between them, which is more value than the 20 energy approvals at A$15.1 billion. The portal files data centres with water and telecommunications. The Pipeline gives them a sector of their own, because they are a different kind of project with different conditions.

Ten data centres were worth more than all 20 energy approvalsCapital investment value approved by sector, 12 months to 22 November 2026.
Source: claused. Pipeline, NSW Planning Portal records, 22 November 2026.
Show the data
SectorApprovalsValue
Housing and commercial129A$21.4bn
Data centres10A$15.3bn
Energy20A$15.1bn
Transport18A$5.5bn
Health and education13A$4.3bn
Mining9A$0.9bn
Industrial13A$0.6bn
Water3A$0.6bn
Other2A$0.1bn

Most housing approvals came through affordable housing pathways

Inside the housing group, the largest single category was in-fill affordable housing, with 45 approvals worth A$6.0 billion. These projects use the affordable housing bonus to reach the State significant pathway. The Housing Delivery Authority pathway accounted for another 29.

In-fill affordable housing was the largest housing pathwayHousing and commercial approvals by type, 12 months to 22 November 2026. 129 approvals.
Source: claused. Pipeline, NSW Planning Portal records, 22 November 2026.
Show the data
TypeApprovalsValue
In-fill affordable housing45A$6.0bn
Housing Delivery Authority29A$4.1bn
Mixed use17A$2.3bn
Seniors housing15A$1.9bn
Residential11A$2.0bn
Build to rent8A$1.4bn
Residential and commercial4A$3.7bn

Three quarters of the value was approved in Greater Sydney

Of the 217 approvals, 166 were in Greater Sydney, worth A$45.6 billion, or 72% of the total. The other 50 were across regional NSW, worth A$18.0 billion, a figure lifted by a handful of large wind and solar farms in the Riverina and the central west. Four of them, two wind and two solar, account for A$9.1 billion.

Greater Sydney took 166 of 217 approvalsApprovals by location. One approval has no recorded location.
Source: claused. Pipeline, NSW Planning Portal records, 22 November 2026.
Show the data
LocationApprovalsValue
Greater Sydney166A$45.6bn
Rest of NSW50A$18.0bn
No location recorded1A$0.1bn

By local government area, Ku-ring-gai had the most approvals with 16, followed by the City of Sydney with 12 and North Sydney and Penrith with 11 each. By value, Blacktown led at A$6.6 billion from four approvals, then the City of Ryde at A$6.1 billion from seven.

What it means for the year ahead

Most of these projects have not started construction. Each now carries a consent of, typically, more than 100 conditions, as we found in how many conditions a NSW consent carries. For contractors the pattern is clear:

  • Urban housing dominates the count. Expect consents with long construction sections: hours, noise, traffic, dilapidation and tree protection, close to neighbours who complain.
  • Data centres are a new major project type. They bring power, water and noise conditions at a scale more familiar from industrial sites.
  • Energy carries fewer conditions but more plans. Biodiversity, heritage and traffic management plans do the heavy lifting.

Frequently asked questions

How many State significant projects did NSW approve in the last year?

217 in the 12 months to 22 November 2026, with a combined capital investment value of A$63.6 billion. Eighteen of them state no value.

Which sectors were approved?

Housing and commercial projects made up 129 of the 217 approvals and A$21.4 billion. Ten data centres were worth A$15.3 billion and 20 energy projects A$15.1 billion. Transport, health and education, mining, industrial and water made up the rest.

Where were the projects?

166 of the 217 approvals were in Greater Sydney, worth A$45.6 billion or 72% of the total. Ku-ring-gai had the most approvals of any council area with 16.

Jake Founder, claused.

claused. is built by a practitioner who ran environmental approvals and compliance on major Australian infrastructure, and got tired of proving compliance out of spreadsheets. About claused.

Last reviewed 22 November 2026. General information, not legal advice. The conditions that bind a project are the ones written in its own instruments.

Keep reading

All 26 guides
Compliance

How many conditions does a NSW consent carry? We counted 429

The median NSW State significant consent carries 111 numbered conditions over 31 pages, and more than half carry 100 or more. The spread by sector, why schools carry more than wind farms, and what it means for the register.

6 min read · 22 Nov 2026

Guides

How long NSW major project approvals take, by who decides

From lodgement to determination, the median NSW State significant approval took 555 days at the department, 502 with the Minister and 955 at the Independent Planning Commission. Why the gap, and what it means for mobilisation.

6 min read · 22 Nov 2026