How long NSW major project approvals take, by who decides

Who this is forContractors and delivery teams planning mobilisation around a NSW State significant approval, and proponents setting expectations with a board or a funder.
A NSW State significant approval takes a long time, and the time it takes depends heavily on who makes the decision. We measured every approval of State significant development and infrastructure determined in the two years to 22 November 2026 where the portal records both a lodgement date and a determination date. That is 334 decisions.
The department decides most projects in about 18 months
The Department of Planning, Housing and Infrastructure, acting under delegation, determined 261 of the 334 approvals. Its median was 555 days from lodgement to determination, about 18 months. A quarter of its decisions came within 425 days, and a quarter took longer than 880.
The Minister determined 30, with a median of 502 days. The Independent Planning Commission determined 42, with a median of 955 days, close to two and a half years. One approval in the period came from the Land and Environment Court.
Show the data
| Decided by | Approvals | Lower quarter | Median | Upper quarter | Top tenth from |
|---|---|---|---|---|---|
| Minister for Planning | 30 | 392 | 502 | 737 | 1178 |
| Department of Planning | 261 | 425 | 555 | 880 | 1287 |
| Independent Planning Commission | 42 | 637 | 955 | 1374 | 1859 |
| Land and Environment Court | 1 | 927 | 927 | 927 | 927 |
Why the Commission takes longer
The comparison is not like for like. A project reaches the Commission because it meets a referral trigger, which has historically included a large number of unique public objections, an objection from the local council, or a reportable political donation by the applicant. Those are the contested projects, so they carry more submissions to respond to and more issues to resolve before a decision.
The Commission's time also includes the department's full assessment before referral. The Commission then holds its own meetings and, often, a public hearing before it determines. Most of the extra time is the contest, not the Commission.
Housing is the exception
The department reports that State significant housing is moving much faster, at an average of 241 days end to end in the six months to October 2026, against its target of 275. That figure is an average for housing only and is measured the department's way, so it should not be set against the medians above. It does show where the system's priority sits. We look at that pathway in State significant housing in NSW.
Where the time goes
Every State significant application passes through the same broad stages, and the clock in the chart above covers the stretch from lodgement to determination.
- Before lodgementAssessment requirements issuedThe department sets the Secretary's environmental assessment requirements, which define what the environmental impact statement must cover.
- LodgementEnvironmental impact statement lodgedThe clock in this article starts here.
- ExhibitionPublic exhibition and submissionsAgencies, the council and the community make submissions on the application.
- ResponseThe applicant responds to submissionsOften the longest stretch: further studies, design changes and amended applications.
- AssessmentThe department assesses and drafts conditionsThe assessment report and the recommended conditions are written.
- DeterminationApproved with conditions, or refusedBy the department, the Minister or the Commission. The conditions now bind the project.
What it means for delivery
The practical effect of an 18-month assessment is that conditions arrive late in the delivery sequence. By the time the consent is issued, a contractor is often already engaged and mobilising, and every condition that must be satisfied before construction starts lands at once: management plans, the Environmental Representative, notifications, dilapidation surveys, the first independent audit to be booked.
- Read the recommended conditions early. Where a project goes to the Commission, the department's assessment report and recommended conditions are published before the decision. Use them to start drafting plans.
- Build the pre-construction list before the consent. Most conditions that apply before construction follow a familiar pattern. Draft against the pattern and adjust to the final wording.
- Price the wait. A quarter of department decisions took more than 880 days. Programme and tender validity should allow for the upper quarter, not the median.
The weeks after approval are covered step by step in the first 30 days after a NSW approval.
Frequently asked questions
How long does a NSW State significant approval take?
For approvals determined in the two years to 22 November 2026, the median time from lodgement to determination was 555 days where the department decided, 502 days for the Minister and 955 days for the Independent Planning Commission.
Why does the Independent Planning Commission take longer?
Projects reach the Commission because they meet a referral trigger, such as a large number of objections or an objection from the council. They are the contested projects, and the Commission's time includes the department's full assessment before referral and the Commission's own meetings and hearings.
Is State significant housing faster?
The department reports an average of 241 days end to end for State significant housing in the six months to October 2026, against a target of 275. It is an average measured the department's way, so it is not directly comparable with the medians in this guide.
Last reviewed 22 November 2026. General information, not legal advice. The conditions that bind a project are the ones written in its own instruments.