The first 30 days after a NSW major project approval

Who this is forProject directors, environmental managers and delivery leads on a NSW State significant project in the weeks after the consent is issued, whether working for the proponent or the contractor.
A NSW State significant approval typically takes a year and a half to arrive, as we found in how long NSW approvals take. When it does, the delivery team usually wants to start yesterday. The conditions that apply before construction are where that ambition meets the consent, and the first month decides whether construction starts on time and in compliance.
This guide follows the post-approval requirements the Department of Planning, Housing and Infrastructure published in March 2026 and the standard conditions it uses for State significant development. Your consent is what binds you. Where its wording differs from what is written here, follow the consent.
Week one: read it, and build the register
Before anything else, read the consent end to end with the people who will deliver it. Then turn it into a register: one row per condition, quoted word for word, with the instrument, the condition number, the stage it applies to, the trigger, an owner and the evidence that will close it. Split lettered parts into their own rows. The register template has the columns.
Then sort the register by stage. Most consents are built around the phases of the project, so the conditions that must be met before construction can start are usually easy to pull out. That list is your first month.
The work that comes before construction
- Day 1Consent issuedThe conditions bind the project from now. Download the consent and the approved documents it lists.
- Week 1Register built and owners namedEvery condition in a register, sorted by stage, each with a named owner.
- Weeks 1 to 4Management plans finalised and submittedThe CEMP and sub-plans the consent calls up, prepared in consultation with the agencies it names, and submitted for approval where the consent requires it.
- Weeks 2 to 4Independent audit team proposedThe Planning Secretary must agree the audit team in writing, and the request must go in at least eight weeks before the end of the period in which the audit is due.
- Before noticePre-construction surveys and approvalsDilapidation surveys, pre-clearance surveys, road occupancy and other approvals the consent or the plans require before work.
- 1 month beforeNotification of commencementThe standard industry conditions ask for at least one month's notice of construction and of each stage. Some consents ask for 48 hours. Read yours.
- 48 hours beforeProject website liveApprovals, approved plans and, later, monitoring summaries, compliance reports and audit reports, published as they are obtained or approved.
- ConstructionConstruction startsThe first independent audit falls due between four and twelve weeks from here.
Management plans: the long pole
If anything delays the start, it is usually the management plans. A consent can require a construction environmental management plan with sub-plans for noise and vibration, soil and water, traffic, heritage, biodiversity and air quality, each prepared in consultation with named agencies and approved before the relevant work starts. Agency consultation takes weeks and approval takes longer.
- Start before the consent. Draft against the recommended conditions where they are published, or against the pattern of earlier consents for the same kind of project.
- Stage it. Many consents allow plans to be prepared for a stage of the work. Early works can often start under a narrower plan while the full plan is approved.
- Write commitments you can evidence. Every frequency, limit and hold point in a plan becomes an obligation once it is approved. See management plan commitments.
The independent auditor
Under the March 2026 requirements, the first independent audit must be carried out between four and twelve weeks after construction starts, and then at intervals of no more than 26 weeks. The lead auditor must hold lead or principal ISO 14001 auditor certification from a recognised body, or other suitable qualifications, and experience with the type of project. The Planning Secretary must agree the team in writing before the audit.
That approval takes time, so propose the team early. Auditors who know the project type are in demand. Independent environmental audits covers what they test.
Incidents and non-compliances from day one
The reporting duties start with the consent, not with construction. Under the department's standard conditions, an incident must be notified immediately after the applicant becomes aware of it, followed by written notification within seven days and a detailed report within 30. A non-compliance must be reported within seven days of becoming aware of it. Newer consents route both through the Major Projects portal. If the project also holds an environment protection licence, the EPA's own clocks apply as well, including the 21-day non-compliance report.
A checklist for the first month
- Consent and every approved document it lists, downloaded and filed.
- A register of every condition, by stage, with owners.
- The list of pre-construction conditions, with a date for each.
- Management plans in consultation, with a submission date.
- Independent audit team proposed to the department.
- Surveys and secondary approvals booked.
- Notification of commencement drafted, with the period your consent requires.
- Project website built and ready to go live.
- Incident and non-compliance process written, tested and known on site.
- Contract flow-down: the evidence each subcontractor must provide, written into the subcontract.
Frequently asked questions
How much notice of commencement does a NSW State significant consent require?
It depends on the consent. The department's standard conditions for industry projects ask for at least one month's notice of construction and of each stage. Some consents, particularly for social infrastructure, ask for 48 hours. Your consent sets the period.
When is the first independent audit due?
Under the March 2026 Independent Audit Post Approval Requirements, between four and twelve weeks after construction starts, and then at intervals of no more than 26 weeks. The Planning Secretary must agree the audit team in writing first.
Are compliance reports required during construction?
Not under the March 2026 Compliance Reporting Post Approval Requirements. There is no compliance reporting before or during construction. The independent audits do that job.
How quickly must an incident be reported?
Under the department's standard conditions, immediately after becoming aware of it, with written notification within seven days and a detailed report within 30. A non-compliance must be reported within seven days. Check your consent for its own wording.
Last reviewed 22 November 2026. General information, not legal advice. The conditions that bind a project are the ones written in its own instruments.