Skip to content
claused.

Independent environmental audits on NSW major projects

Jake, FounderPublished 22 November 20267 min read
A silt fence and standing water on a construction site after rain

Who this is forEnvironmental managers, project managers and contractors on NSW State significant projects with an independent audit coming up, and anyone responding to the findings of one.

On a NSW State significant project, the independent audit is the main way anyone outside the project tests compliance during construction. The Department of Planning, Housing and Infrastructure updated its Independent Audit Post Approval Requirements in March 2026, alongside new compliance reporting requirements. Together they make the audit more important than it was, because there are no longer any compliance reports during construction. The audit is the check.

4 to 12 weeksFirst audit, after construction starts
26 weeksAt most, between construction audits
2 monthsTo submit the report and responseFrom the last day of the site inspection
PublicReports go on the Major Projects website

When audits happen

The March 2026 requirements set the schedule by phase. During construction the first audit is carried out between four and twelve weeks after construction starts, and later audits at intervals of no more than 26 weeks. During operation the first audit falls between 12 and 26 weeks after operation starts, and then at most every three years. Closure audits follow their own timing. The Planning Secretary can agree or direct a different schedule, and older consents may still use the earlier requirements, so check which version your consent calls up.

  1. Before
    Audit team agreedNSWThe Planning Secretary agrees the audit team in writing. The request must go in at least eight weeks before the end of the period in which the audit is due.
  2. Weeks 4 to 12
    First construction auditConstructionBetween four and twelve weeks after construction starts.
  3. Every 26 weeks
    Further construction auditsConstructionAt intervals of no more than 26 weeks until construction is complete.
  4. Weeks 12 to 26
    First operational auditOperationBetween 12 and 26 weeks after operation starts.
  5. Every 3 years
    Further operational auditsOperationAt intervals of no more than three years.

Who the auditor is

The lead auditor must hold lead or principal ISO 14001 environmental auditor certification from a recognised body, such as Exemplar Global, IRCA or PECB, or other suitable qualifications, and experience with the type of project being audited. The team can include specialists for technical areas. The auditor must be independent of the project, and the Planning Secretary must agree the team in writing before the audit.

What the auditor tests

An independent audit tests compliance with the consent and with the documents the consent makes enforceable, including the approved management plans. In practice the auditor works condition by condition and commitment by commitment, and asks the same question each time: show me the evidence.

  • The conditions. Each condition that applied in the audit period, and whether the evidence shows it was met.
  • The plans. Whether the approved plans were implemented as written: the inspection frequencies, the monitoring, the hold points.
  • The site. A site inspection to see whether controls in the field match what the records say.
  • The previous audit. Whether the actions from the last audit were closed out.

What makes a good evidence pack is covered in the condition evidence pack.

The report, the response and publication

The audit report and the proponent's response to its findings are submitted together, within two months of the last day of the site inspection. Audit reports and responses are made public on the Major Projects website, with redaction allowed where it is justified. A finding of non-compliance in an audit report is therefore a public record, and so is your response to it.

Most of the department's compliance activity this year has been inspectionNSW planning compliance activity, July 2026 to 2 November 2026, all projects.
Source: NSW Department of Planning, Housing and Infrastructure, record of compliance activities, updated 2 November 2026.
Show the data
ActivityNumber
Inspections and surveillance230
Penalty notices4
Official cautions1
Orders1
Enforceable undertakings0
Prosecutions0

How to prepare

  1. Agree the auditor early. Propose the team well before construction starts so the first audit window is not missed.
  2. Keep the register current. The auditor will ask for the conditions and commitments that applied in the period, with a status for each. A register reconciled after every modification and plan revision is the starting point.
  3. Make the evidence at the time. Inspection records, monitoring results, notifications and training records made when the work was done, with a date and a place, hold up. Records rebuilt for the audit do not.
  4. Close the last audit. Track every finding to a closed action with evidence before the next audit starts.
  5. Walk the site first. Do your own inspection a week before the auditor's and fix what you find.

Frequently asked questions

How often are independent audits required on NSW State significant projects?

Under the March 2026 requirements, during construction the first audit falls between four and twelve weeks after construction starts and later audits at intervals of no more than 26 weeks. During operation the first falls between 12 and 26 weeks after operation starts, then at most every three years. The Planning Secretary can agree or direct a different schedule.

Who can be the independent auditor?

A lead auditor with lead or principal ISO 14001 auditor certification from a recognised body such as Exemplar Global, IRCA or PECB, or other suitable qualifications, and experience with the type of project. The Planning Secretary must agree the team in writing.

Are audit reports published?

Yes. The report and the proponent's response are submitted together within two months of the last day of the site inspection, and are made public on the Major Projects website. Redaction is allowed where justified.

Jake Founder, claused.

claused. is built by a practitioner who ran environmental approvals and compliance on major Australian infrastructure, and got tired of proving compliance out of spreadsheets. About claused.

Last reviewed 22 November 2026. General information, not legal advice. The conditions that bind a project are the ones written in its own instruments.

Keep reading

All 26 guides
Guides

The first 30 days after a NSW major project approval

A consent is issued and the clock starts. What to do in the first month of a NSW State significant approval: the register, the plans, the notifications, the website, the auditor and the incident process, in order.

8 min read · 22 Nov 2026

One email when a guide is published.

New guides and changes to the legislation they cite. About one a fortnight. Unsubscribe at any time.