Nichols Road Quarry Intensification, Nubeena
Quarries and extractive · Nubeena · Tasmania
- To a 132 kV line
- 43 km
Overview
Gadtech Pty Ltd is proposing to intensify operations Nichols Quarry, located off Nichols Road, less than 1km from the township of Nubeena. The proposal involves a production increase from 10,000 cubic metres up to 20,000 cubic metres of rock and gravel per year, and includes the crushing and screening of material. No change to the Maximum Extraction Area approved by the current Permit is proposed. No new infrastructure is proposed.
- Location
- Nubeena (locality centre; the EPA names the locality, not the site), Tasmania-43.1000, 147.7120
- Value
- Not published
- Approving authority
- Board of the EPA Tasmania
- Distance to the grid
- 43 km to a 220 kV line. 42 km to Lindisfarne substation (220 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- Planning
- AssessmentNowLodged 29 Apr 2025
- Approved
- Construction
- Operating
EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.
- EPA assessment, Nichols Road Quarry (Class 2B)Tasmania · Board of the EPA Tasmania29 Apr 2025 → pending1 year 6 months so farIn assessment↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each containsSite constraints
Site constraints
Nearby
- Reverse Osmosis Facility, NubeenaIn assessment0.0 km
- Noyes Road Quarry Capacity Increase, White BeachIn assessment5 km
- White Beach Quarry Capacity Increase, White BeachApproved5 km
- Penitentiary Conservation Project, Port Arthur Historic SiteIn planning12 km
- Sandford Sand Mine and Washing Facility, Expansion and IntensificationIn assessment21 km
- Rokeby Road - South Arm Road Upgrades: Acton Road Intersection UpgradeIn planning · $55m29 km
Sources
- EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Commenced. Retrieved 25 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Spotted an error? Tell us.
Get every change to quarries and extractive projects in TAS, and the firms you follow, in the Monday briefing.