ApprovedNo EPBC referral

Eddy Creek Quarry Upgrade, Lonnavale

Quarries and extractive · Lonnavale · Tasmania

To a 132 kV line
16 km

Overview

The proposal relates to an upgrade of the Eddy Creek Quarry, located off Eddy Road, Lonnavale from an existing level 1 activity extracting up to 4,999 cubic metres of dolomite rock per annum, to a level 2 activity extracting up to 20,000 cubic metres (32,000 tonnes) of dolomite rock per annum.

Location
Lonnavale (locality centre; the EPA names the locality, not the site), Tasmania-42.9655, 146.7725
Value
Not published
Approving authority
Board of the EPA Tasmania
Distance to the grid
16 km to a 220 kV line. 42 km to Chapel Street substation (220 kV).Straight line to operational lines and substations of 132 kV or more.

Approval progress

1 approval on record
  1. Planning
  2. Assessment
  3. ApprovedNow

EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.

  • EPA assessment, Eddy Creek Quarry Upgrade, LonnavaleTasmania · Board of the EPA Tasmania
    Assessment completed↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and TAS maps…
  1. Lonnavale Broodstock RAS and Pre-Smolt Facility, LonnavaleIn assessment0.0 km
  2. Edgar Dam Strengthening ProjectIn planning21 km
  3. Sawmill and Pyrolysis Facility, HuonvilleApproved24 km
  4. Geeveston Wastewater Treatment Plant, Discharge Relocation, Port HuonApproved25 km
  5. Whale Point Nursery Intensification and Expansion, Port HuonApproved25 km
  6. Catos Hill Quarry Capacity Increase, CradocApproved26 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Completed. Retrieved 25 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Spotted an error? Tell us.

Get every change to quarries and extractive projects in TAS, and the firms you follow, in the Monday briefing.