The new federal approval tests from 1 December 2026: what changes for contractors

Jake, FounderPublished 22 November 20267 min read
A silt fence across disturbed ground on a construction site

Who this is forContractors, proponents and environmental advisors on projects that need, or may need, approval under the Commonwealth EPBC Act, and anyone tendering for work on projects still in federal assessment.

The rewrite of the EPBC Act has been arriving in stages since the Environment Protection Reform Act 2025 received assent on 1 December 2025. The National Environmental Protection Agency started on 1 July 2026, the first National Environmental Standards in August, and the new audit and stop-work powers soon after. The biggest change to how projects are approved commences on 1 December 2026, unless it was proclaimed earlier: the new approval tests.

3New approval testsStandards, unacceptable impact, net gain
4National Environmental Standards in force
30Business days for a streamlined decisionNot for fossil fuel projects
UnchangedApprovals already grantedExisting conditions stay as they are

The reform timetable

  1. 1 Dec 2025
    Reform Acts receive assentFederalThe Environment Protection Reform Act 2025 and the National Environmental Protection Agency Act.
  2. 1 Jul 2026
    National EPA startsFederalThe new agency takes on compliance, enforcement and permits, and keeps public registers of decisions.
  3. 21 and 22 Aug 2026
    Four National Environmental Standards madeFederalMatters of national environmental significance, offsets, community engagement, and data and information.
  4. 24 Aug 2026
    Audit powers and environment protection ordersFederalAudits without notice and stop-work orders of up to 28 days. See EPBC stop-work orders and audits.
  5. Oct 2026
    First environment protection order reportedFederalClearing of about 1,600 hectares near Mount Garnet in north Queensland stopped over sediment risk to the Great Barrier Reef.
  6. 1 Dec 2026
    New approval tests commenceFederalStandards consistency, unacceptable impacts and net gain, with streamlined assessment, bioregional planning and restoration charges.
  7. 1 Jul 2027
    Regional Forest Agreement exemption endsFederal

The three new tests

From commencement, the Minister cannot approve an action under the EPBC Act unless it passes three tests, except for a project approved as a national interest proposal.

TestWhat it means
Consistency with the StandardsThe decision must be consistent with each National Environmental Standard as it stands at the time. Four are in force: matters of national environmental significance, offsets, community engagement, and data and information.
No unacceptable impactAn action that would have an unacceptable impact on a protected matter cannot be approved. Unacceptable impact is defined separately for each kind of protected matter, in terms of serious loss, damage or impairment.
Net gainAny significant impact left after avoiding, mitigating and repairing must be compensated so that the protected matter ends up better off. That can be done through offsets, a restoration contribution, or both.

New pathways and charges

  • Streamlined assessment. A decision within 30 business days, without requests for further information, for projects that come in ready. Not available for fossil fuel projects.
  • National interest proposals. Can be approved despite failing the Standards, the unacceptable impact test or net gain. Not available for fossil fuel projects.
  • Restoration charges. A proponent can pay a charge instead of delivering its own offsets. The Restoration Contributions Holder must generally start restoration within three years of payment.
  • Bioregional plans. Made with the states, they can set development zones where certain classes of action need no separate EPBC approval, and conservation zones where certain actions are prohibited.

Which projects the tests reach

The transitional rules turn on where a project sits in the federal process on the day the tests commence.

Where the project isWhat applies
Already approvedThe approval and its conditions are unaffected. A later variation may bring in new decision requirements.
Referred, with an assessment pathway decidedStays on its existing track.
Referred, but no pathway decided yetMoves onto the new pathways.
Referred on or after commencementThe new tests apply in full.

The enforcement side of the reform is different. Environment protection orders are not limited to projects approved under the new tests. Whether the new power to audit without notice reaches approvals granted before the reforms was still unsettled when this guide was written, with commentators divided. A contractor on a project approved years ago should plan as if it does.

What changes for contractors

The tests are decided before a contractor arrives, so their effect on site comes through the conditions. Expect approvals granted under the new tests to carry more detailed offset and restoration conditions, tighter limits on where and how much clearing can happen, and more reporting written to the data and information Standard.

  • Read the EPBC conditions as closely as the state ones. A major project often holds both. Put both in one register, each with its instrument named.
  • Expect clearing limits to be enforced. The first stop-work order was about clearing. Survey, mark and record clearing boundaries before work and keep the record.
  • Price the uncertainty on projects in assessment. A project still waiting for a federal decision may come out with different conditions from the ones the tender assumed.
  • Assume an audit can arrive without notice. Keep the evidence for every EPBC condition current, not assembled for an annual report.

Frequently asked questions

What changes under the EPBC Act on 1 December 2026?

The new approval tests commence: a decision must be consistent with the National Environmental Standards, an action with an unacceptable impact on a protected matter cannot be approved, and residual significant impacts must be compensated to achieve a net gain. Streamlined assessment, bioregional planning and restoration charges start at the same time, unless proclaimed earlier.

Do the new tests apply to projects already approved?

No. Existing approvals and their conditions are unaffected, although a later variation may bring in new decision requirements. Projects already referred with an assessment pathway decided stay on their track. Projects referred without a pathway decision move onto the new pathways.

What is the streamlined assessment pathway?

A federal decision within 30 business days, without requests for further information, for projects that come in ready. It is not available for fossil fuel projects.

What does net gain mean?

Any significant impact that remains after avoiding, mitigating and repairing harm must be compensated so the protected matter ends up better off. That can be done through offsets, a restoration contribution charge, or both.

Jake Founder, claused.

claused. is built by a practitioner who ran environmental approvals and compliance on major Australian infrastructure, and got tired of proving compliance out of spreadsheets. About claused.

Last reviewed 22 November 2026. General information, not legal advice. The conditions that bind a project are the ones written in its own instruments.

Keep reading

All 26 guides
Legislation

POEO Act penalties explained for contractors

Maximum penalties under the POEO Act after the 2024 increases, the penalty notice amounts, and how NSW compares with the new federal EPBC penalties. Who gets fined, how much, and the conditions that most often lead to enforcement.

8 min read · 20 Jan 2026

One email when a guide is published.

New guides and changes to the legislation they cite. About one a fortnight. Unsubscribe at any time.