In planningEPBC 2026/10672 · EPBC referred, decision pending

Yarrabee Coal Mine Project

Mining · Queensland

To a 132 kV line
31 km

Overview

Last activity 2026
Location
Queensland-23.3085, 149.0475
Value
Not published
Approving authority
Australian Government (DCCEEW)
Distance to the grid
31 km to a 132 kV line. 35 km to 275 kV. 31 km to Bluff substation (132 kV).Straight line to operational lines and substations of 132 kV or more.

Approval progress

1 approval on record
  1. PlanningNow

The EPBC referral is the one instrument on record for this project. Later steps appear here as the public registers record them.

  • EPBC Act referralCommonwealth · Australian Government (DCCEEW) · EPBC 2026/10672
    Referred, decision pending↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and QLD maps…
  1. Yarrabee Coal Mine Continuation ProjectIn planning4 km
  2. Jellinbah Coal Mine-Central North ExtensionApproved12 km
  3. Development and operation of the Star Coal Project Bulk Sample ProjectIn planning21 km
  4. Washpool Coal ProjectIn planning34 km
  5. Washpool Coking Coal Bulk Sample ProjectIn planning34 km
  6. Gemini Rail Loop ProjectIn assessment41 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. EPBC Act referrals, Australian GovernmentLicence: CC BY 4.0. Retrieved 22 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Spotted an error? Tell us.

Get every change to mining projects in QLD, and the firms you follow, in the Monday briefing.