Decided 28 months after its first record on the NSW portal. Of the 55 NSW generation and storage projects that entered the portal from August 2020 and have been decided, half took 33 months or less.

Decided, 28 months
Half of 55 comparable cases decided by June 2024
$545m
Capital investment value
28 mo
Time to decision
Typical 33 mo
100
Construction jobs
  • StateState significant development, SSD-27014706

    Approved. NSW Department of Planning. Lodged 27 August 2021. Decided 21 December 2023.

    View record

Constraints

Public maps, asked when this page opens · within 5 km

Checking national and NSW maps…

Facts and sources

Location
6773 Goolma Road, Wuuluman, Dubbo Regional, New South Wales
Owner
Not published
Contractors
Not named in a public source yet
Value
$545m, capital investment value
Jobs
100 during construction, 2 once operating
Last activity
30 July 2026
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 21 October 2026.
  2. NSW Major Projects documentsCapital investment value stated in the Department's notice of decision, given as an approximate figure. Document: SSD Notice of Decision.pdf. Licence: CC BY 4.0. Retrieved 21 October 2026.