Where the approval stands
How this is worked outDecided 28 months after its first record on the NSW portal. Of the 55 NSW generation and storage projects that entered the portal from August 2020 and have been decided, half took 33 months or less.
Decided, 28 months
- $545m
- Capital investment value
- 28 mo
- Time to decision Typical 33 mo
- 100
- Construction jobs
- StateState significant development, SSD-27014706
Approved. NSW Department of Planning. Lodged 27 August 2021. Decided 21 December 2023.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Facts and sources
- Location
- 6773 Goolma Road, Wuuluman, Dubbo Regional, New South Wales
- Owner
- Not published
- Contractors
- Not named in a public source yet
- Value
- $545m, capital investment value
- Jobs
- 100 during construction, 2 once operating
- Last activity
- 30 July 2026
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 21 October 2026.
- NSW Major Projects documentsCapital investment value stated in the Department's notice of decision, given as an approximate figure. Document: SSD Notice of Decision.pdf. Licence: CC BY 4.0. Retrieved 21 October 2026.