Batteries and pumped hydro · Energy

Orana Battery Energy Storage System -

Under constructionEPBC: Referral decided2 modifications
Location
Goolma Road, approximately 2km north-east of Wellington, Dubbo Regional, New South Wales
Value
Not published
Owner
Wellington Battery ProjectCo Pty Ltd
Contractors
Not named in a public source yet
State approval
Approved
Federal approval (EPBC)
Referral decided
Last activity
2 September 2025
See it on the map

Approvals

  • StateSSD Modifications, SSD-45242780

    Approved. NSW Department of Planning. Lodged 18 July 2025.

    View record
  • FederalEPBC Act referral, EPBC 2023/09512

    Referral decided. Australian Government (DCCEEW).

    View record

Nearby projects

Sources

  1. EPBC Act referrals, Australian GovernmentLinked to this project by name and location. Licence: CC BY 4.0. Retrieved 20 October 2026.
  2. AEMO Generation Information, July 2026AEMO status: in commissioning, 415 MW, full commercial use June 2026. Licence: AEMO copyright permissions, with attribution. Retrieved 20 October 2026.
  3. NSW Major Projects portalKnown from its modification record. The original application is not on the portal. Licence: CC BY 4.0. Retrieved 20 October 2026.

Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.