Skip to content
In planningSSD-10487 · No EPBC referral

Tuggerah Battery Energy Storage System

Batteries and pumped hydro · 63-69 Lake Road, Tuggerah 2259 · Central Coast · New South Wales

To a 132 kV line
0.2 km

Overview

Last activity 20 November 2026
Location
63-69 Lake Road, Tuggerah 2259, Central Coast, New South Wales-33.3087, 151.4301
Value
Not published
Approving authority
NSW Department of Planning
Distance to the grid
0.2 km to a 132 kV line. 0.3 km to 330 kV. 0.3 km to Tuggerah substation (330 kV).Straight line to operational lines and substations of 132 kV or more.
NSW portal case
SSD-10487First record 20 November 2026

Approval progress

1 approval on record · Assessment requirements issued
  1. PlanningNowFirst record 20 Nov 2026

State significant development is the one instrument on record for this project. Later steps appear here as the public registers record them.

  • State significant developmentNew South Wales · NSW Department of Planning · SSD-10487
    First record 20 Nov 2026
    Not yet lodged↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and NSW maps…

Comparable projects

Batteries and pumped hydro projects in New South Wales. Grey is the middle half of them, the marker is this project.
  • Modifications14 comparable projectsNone0.9 on average, half have 1 or fewer

Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.

  1. Lake Road Battery Energy Storage SystemIn planning · $350m0.1 km
  2. Woolworths Regional Distribution Centre Expansion, WyongWithdrawn · $68m8 km
  3. Buttonderry Waste FacilityWithdrawn11 km
  4. Central Coast Quarter - Stage 3 (Eastern Tower)Withdrawn · $40m15 km
  5. Northside Precinct West GosfordIn planning · $557m15 km
  6. 70 Mann St Gosford Mixed DevelopmentApproved16 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
  3. NSW Major Projects, case recordDetermination authority, portal stage and modification cases. Licence: CC BY 4.0. © State of New South Wales and Department of Planning, Housing and Infrastructure.

Spotted an error? Tell us.