Where the approval stands

$40m
Value estimated at scoping
1.1 km
To a 132 kV line
  • StateState significant development, SSD-47360465

    Withdrawn. NSW Department of Planning. Lodged 16 August 2022.

    View record

Constraints

Public maps, asked when this page opens · within 5 km

Checking national and NSW maps…

Facts and sources

Location
26-30 Mann Street, Gosford, Central Coast, New South Wales
Owner
Not published
Contractors
Not named in a public source yet
Value
$40m, capital investment value estimated at scoping
Distance to the grid
1.1 km to a 132 kV line. 11 km to 330 kV. 1.1 km to West Gosford substation (132 kV).Straight line from the mapped site to operational lines and substations of 132 kV or more.
Last activity
16 August 2022
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.
  2. NSW Major Projects documentsCapital investment value estimated by the applicant at scoping, before the project was assessed. Document: Request for SEARs_20220816000654.pdf. Retrieved 21 October 2026.
  3. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.