Energy · Electricity Generation - Other
Stoney Creek Battery Energy Storage System
In assessment
- Location
- 41 Stoney Creek Road Narrabri NSW, Narrabri Shire, New South Wales
- Value
- Not published
- Owner
- Stoney Creek BESS Pty Ltd
- Contractors
- Not named in a public source yet
- State approval
- In assessment
- Federal approval (EPBC)
- No EPBC referral matched
- Last activity
- 10 September 2024
Approvals
- StateState significant development, SSD-75680468
In assessment. NSW Department of Planning. Lodged 10 September 2024.
View record
Nearby projects
Silverleaf Solar FarmApproved · Energy · $191m · 3 km awayNarrabri Solar FarmWithdrawn · Energy · 5 km awayNarrabri Solar FarmIn planning · Energy · 7 km awayWilga Park Power StationOperating · Energy · 9 km awayNarrabri South Solar FarmApproved · Energy · $82m · 10 km awayNarrabri West Solar FarmIn planning · Energy · 12 km away
Sources
- AEMO Generation Information, July 2026AEMO status: anticipated, 125 MW, full commercial use June 2028. Licence: AEMO copyright permissions, with attribution. Retrieved 20 October 2026.
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.