Somersby Resource Recovery Facility

Waste and recycling · 83 Gindurra Road, Somersby 2250 · Central Coast · New South Wales

To a 132 kV line
0.5 km

Overview

Last activity 12 March 2019
Location
83 Gindurra Road, Somersby 2250, Central Coast, New South Wales-33.4134, 151.2988
Value
Not published
Approving authority
Independent Planning CommissionDetermined by the Independent Planning Commission
Distance to the grid
0.5 km to a 132 kV line. 6.7 km to 330 kV. 0.6 km to Sommersby substation (132 kV).Straight line to operational lines and substations of 132 kV or more.
NSW portal case
SSD-9265First record 12 March 2019

Approval progress

1 approval on record
  1. Planning
  2. AssessmentLodged 12 Mar 2019
  3. WithdrawnDate not published
  • State significant developmentNew South Wales · Independent Planning Commission · SSD-9265
    12 Mar 2019 → date not published
    Withdrawn↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and NSW maps…

Comparable projects

Waste and recycling projects in New South Wales. Grey is the middle half of them, the marker is this project.
  • Modifications33 comparable projectsNone2.3 on average, half have 2 or fewer

Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.

  1. Northside Precinct West GosfordIn planning · $557m3 km
  2. 70 Mann St Gosford Mixed DevelopmentApproved4 km
  3. Central Coast Quarter - Stage 3 (Eastern Tower)Withdrawn · $40m4 km
  4. Central Coast QuarryApproved5 km
  5. Brooklyn - Dangar Island Sewerage SchemeApproved15 km
  6. Brooklyn Island Boat Repair & MaintenanceApproved15 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
  3. NSW Major Projects, case recordDetermination authority, portal stage and modification cases. Licence: CC BY 4.0. © State of New South Wales and Department of Planning, Housing and Infrastructure.

Spotted an error? Tell us.

Get every change to waste and recycling projects in NSW, and the firms you follow, in the Monday briefing.