Skip to content
In planningEPBC 2026/10675 · EPBC referred, decision pending

Joel Joel Battery Energy Storage System Project

Batteries and pumped hydro · Victoria

To a 132 kV line
<0.1 km

Overview

Last activity 2026
Location
Victoria-37.0380, 142.9885
Value
Not published
Approving authority
Australian Government (DCCEEW)
Distance to the grid
Under 0.1 km to a 220 kV line. 0.3 km to Bulgana substation (220 kV).Straight line to operational lines and substations of 132 kV or more.

Approval progress

1 approval on record
  1. PlanningNow

The EPBC referral is the one instrument on record for this project. Later steps appear here as the public registers record them.

Early signals

  1. Date not publishedAwarded Commonwealth underwriting in the Capacity Investment SchemeCIS Tender 3, NEM Dispatchable. 250 MW, 1,000 MWh.Capacity Investment Scheme. A signal is not a planning approval.Awarded
  • EPBC Act referralCommonwealth · Australian Government (DCCEEW) · EPBC 2026/10675
    Referred, decision pending↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and VIC maps…
  1. Watta Wella Renewable Energy ProjectIn assessment5 km
  2. Navarre Green Power HubIn assessment16 km
  3. Normanville Energy ParkIn assessment26 km
  4. Ballyrogan Wind FarmIn planning32 km
  5. Murray Basin Rail Project – Ararat to Maryborough rail line Occupation Crossings UpgradeIn planning32 km
  6. Murray Basin Rail Project - Emu SignallingIn planning53 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. EPBC Act referrals, Australian GovernmentLicence: CC BY 4.0. Retrieved 22 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Spotted an error? Tell us.