In planningNo EPBC referral

Clements Gap BESS

Batteries and pumped hydro · Clements Gap · South Australia

Capacity
60 MW
To a 132 kV line
3.9 km

Overview

Last activity 4 September 2024

Awarded in the Capacity Investment Scheme (CIS South Australia-Victoria tender, announced 4 September 2024). 60 MW (2.4 hour) lithium-ion battery.

Location
Clements Gap (town centre; the tender results do not give the site), South Australia-33.5105, 138.0543
Value
Not published
Technology
Battery, 60 MW, with 143 MWh of storage
Distance to the grid
3.9 km to a 132 kV line. 15 km to 275 kV. 7.1 km to Clements Gap Wind Farm substation (132 kV).Straight line to operational lines and substations of 132 kV or more.

Approval progress

No approval on record
  1. PlanningNow

Early signals

  1. 4 Sept 2024Awarded Commonwealth underwriting in the Capacity Investment SchemeCIS South Australia-Victoria tender, announced 4 September 2024. 60 MW, 143 MWh.Capacity Investment Scheme. A signal is not a planning approval.Awarded

No state or federal approval is recorded yet. Projects appear here once lodged with the approving authority or referred under the EPBC Act. Get an email when that happens.

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and SA maps…

Who's involved

From the registers, certificates and disclosures that name the project
  1. Koolunga BESSIn planning26 km
  2. Bungama SolarOperating36 km
  3. Whyalla Hydrogen Pipeline (WHP)Approved74 km
  4. Cultana Solar Farm projectIn assessment75 km
  5. South Australian Government Renewable Hydrogen Power Station, Electrolysers and Storage FacilityApproved76 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. Capacity Investment Scheme tender results, DCCEEWPlaced at the centre of its suburb (ABS). Licence: CC BY 4.0. Retrieved 22 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.