- Value estimated at scoping
- $37m
- To a 132 kV line
- 2 km
Overview
- Location
- 127 Eagleview Road Minto 2566, Campbelltown, New South Wales-34.0344, 150.8570
- Value
- $37m, capital investment value estimated at scoping
- Approving authority
- NSW Department of Planning
- Distance to the grid
- 2 km to a 330 kV line. 2.3 km to Ingleburn substation (330 kV).Straight line to operational lines and substations of 132 kV or more.
- NSW portal case
- SSD-153495501First record 5 November 2026
Approval progress
- PlanningNowFirst record 5 Nov 2026
- Assessment
- Approved
- Construction
- Operating
State significant development is the one instrument on record for this project. Later steps appear here as the public registers record them.
- State significant developmentNew South Wales · NSW Department of Planning · SSD-153495501First record 5 Nov 2026Not yet lodged↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each contains© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the mapSite constraints
Site constraints
Checking national and NSW maps…
Comparable projects
- Modifications77 comparable projectsNone1.8 on average, half have 2 or fewer
Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.
Nearby
- MOD 5 - Administrative AmendmentIn planning2 km
- Campbelltown Arts Centre ExpansionIn assessment6 km
- Early Works at Lots 4,5 and 8 Buchan Ave, Edmondson ParkIn planning · $25m7 km
- Affordable Housing - Block 20A Edmondson ParkApproved · $97m7 km
- Beach Nourishment WorksApproved8 km
- 126 Kelvin Park Drive, BringellyIn planning15 km
Sources
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 5 November 2026.
- NSW Major Projects documentsCapital investment value estimated by the applicant at scoping, before the project was assessed. Document: Request for SEARs_20261105033240.pdf. Retrieved 9 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
- NSW Major Projects, case recordDetermination authority, portal stage and modification cases. Licence: CC BY 4.0. © State of New South Wales and Department of Planning, Housing and Infrastructure.
Spotted an error? Tell us.
Get every change to education projects in NSW, and the firms you follow, in the Monday briefing.