Commercial and tourism · Property
Wollongong Shopping Centre Redevelopment
Keira Street Wollongong New South Wales Australia · Wollongong City · New South Wales
ApprovedMP06_0209No EPBC referral7 modifications
Where the approval stands
- $312m
- Capital investment value
- 4.6 km
- To a 132 kV line
- 1,190
- Construction jobs
- StatePart 3A major project, MP06_0209
Approved. Minister for Planning. Lodged 8 August 2019. Decided 28 April 2008.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Facts and sources
- Location
- Keira Street Wollongong New South Wales Australia, Wollongong City, New South Wales
- Owner
- Not published
- Contractors
- Not named in a public source yet
- Value
- $312m, capital investment value
- Jobs
- 1,190 during construction, 871 once operating
- Distance to the grid
- 4.6 km to a 132 kV line. 6.1 km to 330 kV. 4.9 km to Spring Hill substation (132 kV).Straight line from the mapped site to operational lines and substations of 132 kV or more.
- Last activity
- 8 August 2019
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
- NSW Major Projects documentsCapital investment value stated in the Department's assessment report. Document: Director General's Assessment Report.pdf. Licence: CC BY 4.0. Retrieved 22 October 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.