Wind · Energy
Wambo Wind Farm
Under constructionEPBC: Approved
- Location
- Queensland
- Value
- $921m, total estimated cost in the state budget
- Capacity
- 500 MW. Wind
- AEMO status
- In commissioning. Full commercial use expected February 2025
- Contractors
- Not named in a public source yet
- State approval
- Not recorded yet
- Federal approval (EPBC)
- Approved
- Last activity
- 2020
Approvals
- FederalEPBC Act referral, EPBC 2020/8727
Approved. Australian Government (DCCEEW).
View record
Nearby projects
Tarong West Wind FarmIn assessment · Energy · 26 km awayKogan North Gas Fields developmentUnder construction · Other · $65m · 55 km awaySurat Gas Project off-tenure pipelines, Surat Basin, QldApproved · Energy · 55 km awayBrigalow Gas Peaking PlantUnder construction · Energy · $391m · 59 km awayTuckeroo Battery Connection ProjectIn planning · Energy · 62 km awayTuckeroo BatteryIn planning · Energy · 62 km away
List every project within 25 km on the map, nearest first, with a CSV for a cumulative impact assessment.
Sources
- Queensland Budget 2026-27, Budget Paper 3 capital statementWambo Wind Farm Stage 1: total estimated cost $468m, $441m spent to 30 June 2026. Licence: CC BY 4.0. Retrieved 20 October 2026.
- Queensland Budget 2026-27, Budget Paper 3 capital statementWambo Wind Farm Stage 2: total estimated cost $453m, $406m spent to 30 June 2026. Licence: CC BY 4.0. Retrieved 20 October 2026.
- EPBC Act referrals, Australian GovernmentLicence: CC BY 4.0. Retrieved 20 October 2026.
- AEMO Generation Information, July 2026AEMO status: in commissioning, 500 MW, full commercial use February 2025. Licence: AEMO copyright permissions, with attribution. Retrieved 21 October 2026.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.