Solar · Energy

Wallaroo Solar Farm

Lot 1 DP544209 and Lot 2 DP602262 Wallaroo, Yass Valley Council Region · Yass Valley · New South Wales

ApprovedSSD-9261283No EPBC referral
-35.1926, 148.9945Open the map
© OpenStreetMap · OpenMapTiles · OpenFreeMap

Where the approval stands

How this is worked out

Decided 48 months after its first record on the NSW portal. Of the 63 NSW generation and storage projects that entered the portal from August 2020 and have been decided, half took 34 months or less.

Decided, 48 months
Half of 63 comparable cases decided by July 2023
$170m
Value estimated at scoping
73
Conditions of consent
Counted from its numbering
48 mo
Time to decision
Typical 34 mo
  • StateState significant development, SSD-9261283

    Approved. Independent Planning Commission. Lodged 11 September 2020. Decided 10 September 2024.

    View record

Constraints

Public maps, asked when this page opens · within 5 km

Checking national and NSW maps…

Facts and sources

Location
Lot 1 DP544209 and Lot 2 DP602262 Wallaroo, Yass Valley Council Region, Yass Valley, New South Wales
Owner
Not published
Contractors
Not named in a public source yet
Value
$170m, capital investment value estimated at scoping
Jobs
5 once operating
Conditions of consent
About 73, counted from the development consent on the NSW Major Projects portalCounted from the document's condition numbering, not read one by one.
Last activity
10 September 2024
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
  2. NSW Major Projects documentsCapital investment value estimated by the applicant at scoping, before the project was assessed, given as an approximate figure. Document: Wallaroo Solar Farm Scoping Report_final v1.1_.pdf. Retrieved 22 October 2026.

Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.