Skip to content
WithdrawnSSD-78073736 · No EPBC referral

Walker Street Residences - 153-157 Walker Street, North Sydney - BTR & Hotel

Commercial and tourism · 153-157 Walker Street · North Sydney · New South Wales

To a 132 kV line
2.1 km

Overview

Last activity 21 November 2024
Location
153-157 Walker Street, North Sydney, New South Wales-33.8377, 151.2095
Value
Not published
Approving authority
NSW Department of Planning
Distance to the grid
2.1 km to a 132 kV line. 4.9 km to 330 kV. 1.8 km to Crows Nest substation (132 kV).Straight line to operational lines and substations of 132 kV or more.
NSW portal case
SSD-78073736First record 21 November 2024

Approval progress

1 approval on record
  1. Planning
  2. AssessmentLodged 21 Nov 2024
  3. WithdrawnDate not published
  • State significant developmentNew South Wales · NSW Department of Planning · SSD-78073736
    21 Nov 2024 → date not published
    Withdrawn↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and NSW maps…

Comparable projects

Commercial and tourism projects in New South Wales. Grey is the middle half of them, the marker is this project.
  • Modifications28 comparable projectsNone2.4 on average, half have 2 or fewer

Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.

  1. 100 Walker Street Build to RentIn planning0.1 km
  2. 132 Arthur Street, North Sydney - Build to RentIn planning0.1 km
  3. Berry/Walker Street RedevelopmentApproved0.1 km
  4. 86-100 Mount Street RedevelopmentApproved0.2 km
  5. Cark Park and Brasserie DevelopmentApproved1 km
  6. 270 Pacific Hwy Crows Nest BTRApproved · $177m1 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
  3. NSW Major Projects, case recordDetermination authority, portal stage and modification cases. Licence: CC BY 4.0. © State of New South Wales and Department of Planning, Housing and Infrastructure.

Spotted an error? Tell us.

Get every change to commercial and tourism projects in NSW, and the firms you follow, in the Monday briefing.