Education · Health and education
UNSW Building E25 Biolink
356 Anzac Parade, Kensington · Randwick City · New South Wales
ApprovedSSD-73456206No EPBC referral1 modification
Where the approval stands
How this is worked outDecided 17 months after its first record on the NSW portal. Of the 85 NSW social infrastructure projects that entered the portal from August 2020 and have been decided, half took 17 months or less.
Decided, 17 months
- $52m
- Capital investment value
- 160
- Conditions of consent Counted from its numbering
- 17 mo
- Time to decision Typical 17 mo
- 184
- Construction jobs
- StateState significant development, SSD-73456206
Approved. NSW Department of Planning. Lodged 17 July 2024. Decided 15 December 2025.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Mixed use development at 32-34 Blenheim St$62mBuilding D14 Redevelopment$118mMixed Use Development at 73 - 109 Belmore Road RandwickValue not publishedAdaptive reuse of the Royal Hall of Industries$47mMixed Use Development and Rezoning at 251-257 Maroubra Road, Maroubra$80mBuild to Rent at 171-183 Oxford St, Bondi Junction$330m
Facts and sources
- Location
- 356 Anzac Parade, Kensington, Randwick City, New South Wales
- Owner
- Not published
- Contractors
- Not named in a public source yet
- Value
- $52m, capital investment value
- Jobs
- 184 during construction
- Conditions of consent
- About 160, counted from the development consent on the NSW Major Projects portalCounted from the document's condition numbering, not read one by one.
- Last activity
- 24 September 2026
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
- NSW Major Projects documentsCapital investment value stated in the Department's assessment report. Document: SSD-SSI Assessment Report.pdf. Licence: CC BY 4.0. Retrieved 22 October 2026.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.