Energy · Energy Generation and Supply (renewable)
Tully Battery Energy Storage System (BESS)
In planningEPBC: Referral decided
- Location
- Queensland
- Value
- Not published
- Owner
- RWE Renewables Australia Pty Ltd
- Contractors
- Not named in a public source yet
- State approval
- Not recorded yet
- Federal approval (EPBC)
- Referral decided
- Last activity
- 2025
Approvals
- FederalEPBC Act referral, EPBC 2025/10377
Referral decided. Australian Government (DCCEEW).
View record
Nearby projects
Mission Beach Helipad and Aviation FacilityIn planning · Transport · 21 km awayPalmerston Highway (Innisfail - Millaa Millaa), 2024 Disaster Recovery Funding Arrangements reconstruction worksUnder construction · Transport · $58m · 43 km awayNicholson Road to Five Mile Creek, Wide Centre Line Treatment Road and Upgrade BridgeIn planning · Transport · 44 km awayRungoo Safety Upgrade, Bowder Creek to Damper Creek, Wide Centre Line TreatmentIn planning · Transport · 52 km awayKaban Green Power Hub, Kaban, QldApproved · Energy · 68 km awayDungeness Breakwater and DredgingIn planning · Transport · 76 km away
Sources
- EPBC Act referrals, Australian GovernmentLicence: CC BY 4.0. Retrieved 20 October 2026.
- AEMO Generation Information, July 2026AEMO status: publicly announced, 200 MW, full commercial use December 2028. Licence: AEMO copyright permissions, with attribution. Retrieved 20 October 2026.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.