Wind · Energy

Thunderbolt Wind Farm

New England Hwy, Kentucky, NSW · Tamworth Regional · New South Wales

ApprovedSSD-10807896No EPBC referral1 modification
-30.7600, 151.3107Open the map
© OpenStreetMap · OpenMapTiles · OpenFreeMap

Where the approval stands

How this is worked out

Decided 42 months after its first record on the NSW portal. Of the 63 NSW generation and storage projects that entered the portal from August 2020 and have been decided, half took 34 months or less.

Decided, 42 months
Half of 63 comparable cases decided by Sept 2023
88
Conditions of consent
Counted from its numbering
42 mo
Time to decision
Typical 34 mo
  • StateState significant development, SSD-10807896

    Approved. Independent Planning Commission. Lodged 4 November 2020. Decided 7 May 2024.

    View record

Constraints

Public maps, asked when this page opens · within 5 km

Checking national and NSW maps…

Facts and sources

Location
New England Hwy, Kentucky, NSW, Tamworth Regional, New South Wales
Owner
Not published
Contractors
Not named in a public source yet
Value
Not published
Conditions of consent
About 88, counted from the conditions of consent on the NSW Major Projects portalCounted from the document's condition numbering, not read one by one.
Last activity
4 July 2025
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.

Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.