Wind · Energy
Thunderbolt Wind Farm
New England Hwy, Kentucky, NSW · Tamworth Regional · New South Wales
ApprovedSSD-10807896No EPBC referral1 modification
Where the approval stands
How this is worked outDecided 42 months after its first record on the NSW portal. Of the 63 NSW generation and storage projects that entered the portal from August 2020 and have been decided, half took 34 months or less.
Decided, 42 months
- 88
- Conditions of consent Counted from its numbering
- 42 mo
- Time to decision Typical 34 mo
- StateState significant development, SSD-10807896
Approved. Independent Planning Commission. Lodged 4 November 2020. Decided 7 May 2024.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Facts and sources
- Location
- New England Hwy, Kentucky, NSW, Tamworth Regional, New South Wales
- Owner
- Not published
- Contractors
- Not named in a public source yet
- Value
- Not published
- Conditions of consent
- About 88, counted from the conditions of consent on the NSW Major Projects portalCounted from the document's condition numbering, not read one by one.
- Last activity
- 4 July 2025
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.