OperatingMP07_0124 · No EPBC referral

Tallawarra B Power Station

Other generation · Tallawarra Power Station Yallah Wollongong Local Government Area 2530 · Wollongong City · New South Wales

Capacity
760 MW
To a 132 kV line
0.1 km

Overview

Last activity 15 August 2024
Location
Tallawarra Power Station Yallah Wollongong Local Government Area 2530, Wollongong City, New South Wales-34.5230, 150.8089
Value
Not published
Technology
Gas, 760 MW
Approving authority
Minister for PlanningDetermined by the Minister for Planning
AEMO status
In service
Distance to the grid
0.1 km to a 132 kV line. 2.8 km to 330 kV. 0.2 km to Tallawarra substation (132 kV).Straight line to operational lines and substations of 132 kV or more.
NSW portal case
MP07_0124First record 23 July 2019, determined 21 December 2010

Approval progress

1 approval on record
  1. Planning
  2. AssessmentLodged 23 July 2019
  3. ApprovedApproved 21 Dec 2010
  4. Construction
  5. OperatingNow
  • State significant infrastructureNew South Wales · Minister for Planning · MP07_0124
    23 July 2019 → 21 Dec 2010under a month
    Approved↗

Modifications

  1. 20 May 2022Modification 3Green Hydrogen Fuel MixDecided 16 Aug 2024, 2 years 2 monthsApproved
  2. 15 May 2020Modification 2Decided 7 Dec 2020, 6 monthsApproved
  3. 29 July 2019Modification 1Decided 6 Apr 2016, under a monthApproved

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and NSW maps…

Who's involved

From the registers, certificates and disclosures that name the project
  1. West Horsley Water InfrastructureApproved5 km
  2. Mixed Use Development at 29 Shellharbour Rd & 25 Grove Cct, Lake IllawarraIn planning · $116m6 km
  3. Subdivision, 20 Iredell Road HuntleyIn assessment · $43m6 km
  4. Subdivision, 179 Calderwood Road, CalderwoodIn assessment · $33m6 km
  5. Northcliffe Drive and Stuart Road, Warrawong, Affordable HousingIn planning8 km
  6. Illawarra Firming Power StationIn planning8 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. AEMO Generation Information, July 2026AEMO status: in service, 760 MW. Licence: AEMO copyright permissions, with attribution. Retrieved 21 October 2026.
  2. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.
  3. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
  4. NSW Major Projects, case recordDetermination authority, portal stage and modification cases. Licence: CC BY 4.0. © State of New South Wales and Department of Planning, Housing and Infrastructure.

Spotted an error? Tell us.

Get every change to other generation projects in NSW, and the firms you follow, in the Monday briefing.