RefusedSSD-6059 · No EPBC referral

Sydney Olympic Park - Site 8C Commercial Development

Commercial and tourism · Murray Rose Avenue 2127 · City of Parramatta · New South Wales

To a 132 kV line
0.3 km

Overview

Last activity 20 February 2019
Location
Murray Rose Avenue 2127, City of Parramatta, New South Wales-33.8460, 151.0695
Value
Not published
Approving authority
Independent Planning CommissionDetermined by the Independent Planning Commission
Distance to the grid
0.3 km to a 132 kV line. 6.1 km to 330 kV. 0.6 km to Olympic park substation (132 kV).Straight line to operational lines and substations of 132 kV or more.
NSW portal case
SSD-6059First record 20 February 2019

Approval progress

1 approval on record
  1. Planning
  2. AssessmentLodged 20 Feb 2019
  3. RefusedDate not published
  • State significant developmentNew South Wales · Independent Planning Commission · SSD-6059
    20 Feb 2019 → date not published
    Refused↗

Modifications

  1. 26 Aug 2015Modification 1Decided 12 Oct 2015, 1 monthApproved

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and NSW maps…

Comparable projects

Commercial and tourism projects in New South Wales. Grey is the middle half of them, the marker is this project.
  • Modifications28 comparable projects12.4 on average, half have 2 or fewer

Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.

  1. 2A and 2B Australia Avenue, Sydney Olympic ParkIn assessment · $207m0.3 km
  2. Ayrfield Colliery - RemediationApproved1 km
  3. 19-25 Bennelong Rd, Homebush BayApproved1 km
  4. Concept Mixed-use Development with Infill Affordable Housing - Blocks A and B -37-39 Hill Rd, Wentworth PointIn planning2 km
  5. 24-32 Walker Street, Rhodes - Residential UnitsApproved2 km
  6. 43 Residential Units & 3 Local ShopsApproved2 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
  3. NSW Major Projects, case recordDetermination authority, portal stage and modification cases. Licence: CC BY 4.0. © State of New South Wales and Department of Planning, Housing and Infrastructure.

Spotted an error? Tell us.