In planningSSD-10488 · No EPBC referral

Southern Parkes Solar Farm

Solar · 388 Coopers Road, Parkes 2870 · Parkes Shire · New South Wales

To a 132 kV line
0.3 km

Overview

Last activity 20 November 2026
Location
388 Coopers Road, Parkes 2870, Parkes Shire, New South Wales-33.1697, 148.0566
Value
Not published
Approving authority
NSW Department of Planning
Distance to the grid
0.3 km to a 132 kV line. 106 km to 330 kV. 7.6 km to Parkes substation (132 kV).Straight line to operational lines and substations of 132 kV or more.
NSW portal case
SSD-10488First record 20 November 2026

Approval progress

1 approval on record · Assessment requirements issued
  1. PlanningNowFirst record 20 Nov 2026

State significant development is the one instrument on record for this project. Later steps appear here as the public registers record them.

  • State significant developmentNew South Wales · NSW Department of Planning · SSD-10488
    First record 20 Nov 2026
    Not yet lodged↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and NSW maps…

Comparable projects

Solar projects in New South Wales. Grey is the middle half of them, the marker is this project.
  • Modifications44 comparable projectsNone1.3 on average, half have 1 or fewer

Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.

  1. Parkes Energy Recovery FacilityIn assessment · $948m5 km
  2. Parkes Solar FarmApproved · $115m6 km
  3. Goobang Junction Rail Upgrade ProjectIn planning · $65m7 km
  4. Pacific National Intermodal FacilityWithdrawn7 km
  5. Parkes Power StationApproved7 km
  6. Goonumbla Solar FarmApproved8 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
  3. NSW Major Projects, case recordDetermination authority, portal stage and modification cases. Licence: CC BY 4.0. © State of New South Wales and Department of Planning, Housing and Infrastructure.

Spotted an error? Tell us.

Get every change to solar projects in NSW, and the firms you follow, in the Monday briefing.