Goshawk Mining Pty Ltd is proposing to intensify the operations at the South Mount Cameron Tin Mine. The mine excavates and processes source gravel to produce tin ore (cassiterite), shingles and sand. Annual extraction and processing limits have varied between 20 000 to 75 000 cubic metres per annum since operations began in 2007, with new extraction and processing limits of 200 000 cubic metres per annum proposed.

Location
South Mount Cameron (locality centre; the EPA names the locality, not the site), Tasmania-40.9995, 147.9660
Value
Not published
Approving authority
Board of the EPA Tasmania
Distance to the grid
87 km to a 220 kV line. 91 km to Georgetown Convertor substation (400 kV).Straight line to operational lines and substations of 132 kV or more.

Approval progress

1 approval on record
  1. Planning
  2. AssessmentNowLodged 19 Aug 2024

EPA assessment is the one instrument on record for this project. Later steps appear here as the public registers record them.

  • EPA assessment, South Mount Cameron Operations (Class 2B)Tasmania · Board of the EPA Tasmania
    19 Aug 2024 → pending2 years 3 months so far
    In assessment↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and TAS maps…
  1. North East Wind - construction and operation of wind turbines and associated infrastructureIn assessment17 km
  2. Abattoir, Ansons Bay Road, St HelensIn assessment20 km
  3. Branxholm Sawmill Intensification, BranxholmApproved28 km
  4. Scottsdale Irrigation Scheme (SIS) - TasmaniaApproved39 km
  5. Dianas Basin Quarry Capacity Increase, St HelensApproved39 km
  6. Vox Resources Tyre Processing, ScottsdaleIn assessment40 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. EPA Tasmania, proposals assessed by the EPAEPA Board assessment: Assessment Commenced. Retrieved 25 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Spotted an error? Tell us.

Get every change to mining projects in TAS, and the firms you follow, in the Monday briefing.