OperatingSSD-59325460 · CFT-699458 · No EPBC referral

Smithfield Battery Energy Storage System

Batteries and pumped hydro · 6 Herbert Place, Smithfield · Cumberland · New South Wales

Capital investment value
$93m
Time to decision
11 mo
Capacity
65 MW
To a 132 kV line
<0.1 km

Overview

Last activity 6 May 2024
Location
6 Herbert Place, Smithfield, Cumberland, New South Wales-33.8493, 150.9489
Value
$93m, capital investment value
Technology
Battery, 65 MW, with 130 MWh of storage
Jobs
30 during construction
Approving authority
NSW Department of PlanningDetermined by the Department of Planning, as the Minister's delegate
AEMO status
In service
Distance to the grid
Under 0.1 km to a 132 kV line. Under 0.1 km to 330 kV. 0.8 km to Guildford substation (132 kV).Straight line to operational lines and substations of 132 kV or more.
NSW portal case
SSD-59325460First record 16 June 2023, determined 7 May 2024

Approval progress

2 approvals on record
  1. Planning
  2. AssessmentLodged 16 June 2023
  3. ApprovedApproved 6 May 2024
  4. Construction
  5. OperatingNow

Early signals

  1. Date not publishedAwarded Commonwealth underwriting in the Capacity Investment SchemeCIS NSW tender. 65 MW, 130 MWh.Capacity Investment Scheme. A signal is not a planning approval.Awarded
  • State significant developmentNew South Wales · NSW Department of Planning · SSD-59325460
    16 June 2023 → 6 May 202410 months
    Approved↗
  • Construction certificateNew South Wales · CFT-699458
    26 Feb 2025
    Certificate issued

Time to decision

Decided 11 months after its first record on the NSW portal. Half of the 65 comparable NSW generation and storage projects decided since August 2020 took 34 months or less. How this is worked out

Decided, 11 months
Half of 65 comparable cases decided by Apr 2026

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and NSW maps…

Comparable projects

Batteries and pumped hydro projects in New South Wales. Grey is the middle half of them, the marker is this project.
  • Time to decision65 comparable projects11 monthsHalf within 34 months
  • Modifications14 comparable projectsNone0.9 on average, half have 1 or fewer

Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.

Who's involved

From the registers, certificates and disclosures that name the project
  • Smithfield BESSOwner
  • Acle ServicesContractor, builder on the construction certificate
  1. Cobra Waste Solutions Resource Recovery FacilityApproved · $3.4m2 km
  2. Fairfield Sustainable Resource Centre ExpansionApproved · $1m3 km
  3. Butu Wargun Drive-Warehouse & Distribution Ctr2Approved4 km
  4. Bettergrow Resource Recovery Facility Wetherill ParkApproved · $16m5 km
  5. 8-16 Picrite Close, Greystanes - WarehouseApproved5 km
  6. Chemsal Chemical Waste - Wetherill ParkApproved5 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. NSW Major Projects documentsCapital investment value stated in the Department's notice of decision, given as an approximate figure. Document: SSD Notice of Decision.pdf. Licence: CC BY 4.0. Retrieved 21 October 2026.
  2. AEMO Generation Information, July 2026AEMO status: in service, 65 MW, 130 MWh. Licence: AEMO copyright permissions, with attribution. Retrieved 21 October 2026.
  3. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.
  4. NSW Planning Portal, construction certificatesConstruction certificate CFT-699458 issued 26 February 2025. Builder named: Acle Services Pty Ltd. Matched to this project by claused. from the site address. © State of New South Wales (Department of Planning, Housing and Infrastructure). Licence: CC BY 4.0. Retrieved 25 November 2026.
  5. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
  6. NSW Major Projects, case recordDetermination authority, portal stage and modification cases. Licence: CC BY 4.0. © State of New South Wales and Department of Planning, Housing and Infrastructure.

Spotted an error? Tell us.