Royal Randwick - Future Music Festival 2013

Commercial and tourism · Alison Road Randwick · Randwick City · New South Wales

To a 132 kV line
0.6 km

Overview

Last activity 20 February 2019
Location
Alison Road Randwick, Randwick City, New South Wales-33.9124, 151.2277
Value
Not published
Approving authority
Independent Planning CommissionDetermined by the Independent Planning Commission
Distance to the grid
0.6 km to a 132 kV line. 3.7 km to 330 kV. 1.6 km to Kingsford substation (132 kV).Straight line to operational lines and substations of 132 kV or more.
NSW portal case
SSD-5394First record 20 February 2019

Approval progress

1 approval on record
  1. Planning
  2. AssessmentLodged 20 Feb 2019
  3. RefusedDate not published
  • State significant developmentNew South Wales · Independent Planning Commission · SSD-5394
    20 Feb 2019 → date not published
    Refused↗

Modifications

  1. 5 Feb 2013Modification 1Decided 6 Mar 2013, 1 monthApproved

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and NSW maps…

Comparable projects

Commercial and tourism projects in New South Wales. Grey is the middle half of them, the marker is this project.
  • Modifications28 comparable projects12.4 on average, half have 2 or fewer

Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.

  1. Building D14 RedevelopmentApproved · $118m0.5 km
  2. Mixed use development at 32-34 Blenheim StIn planning · $62m1 km
  3. Alexandria Health Centre Concept ProposalApproved · $84m3 km
  4. Build to Rent at 171-183 Oxford St, Bondi JunctionIn assessment · $330m3 km
  5. Westfield Bondi JunctionApproved3 km
  6. Affordable Housing Development - Botany Road, MascotApproved3 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
  3. NSW Major Projects, case recordDetermination authority, portal stage and modification cases. Licence: CC BY 4.0. © State of New South Wales and Department of Planning, Housing and Infrastructure.

Spotted an error? Tell us.