Batteries and pumped hydro · Energy
Ridgey Creek Battery Energy Storage System
822 Henry Parkes Way, Parkes NSW 2870 · Parkes Shire · New South Wales
ApprovedSSD-48756517No EPBC referral1 modification
Where the approval stands
How this is worked outDecided 32 months after its first record on the NSW portal. Of the 63 NSW generation and storage projects that entered the portal from August 2020 and have been decided, half took 34 months or less.
Decided, 32 months
- $183m
- Capital investment value
- 32 mo
- Time to decision Typical 34 mo
- 50
- Construction jobs
- StateState significant development, SSD-48756517
Approved. NSW Department of Planning. Lodged 25 September 2022. Decided 5 June 2025.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Facts and sources
- Location
- 822 Henry Parkes Way, Parkes NSW 2870, Parkes Shire, New South Wales
- Contractors
- Not named in a public source yet
- Value
- $183m, capital investment value
- Jobs
- 50 during construction, 2 once operating
- Last activity
- 16 June 2026
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
- NSW Major Projects documentsCapital investment value stated in the Department's notice of decision, given as an approximate figure. Document: Notice of Decision..pdf. Licence: CC BY 4.0. Retrieved 22 October 2026.