Solar · Energy
Richmond Valley Solar Farm
420 Avenue Road, Myrtle Creek NSW 2469 · Richmond Valley · New South Wales
ApprovedSSD-41020244No EPBC referral
Where the approval stands
How this is worked outDecided 42 months after its first record on the NSW portal. Of the 63 NSW generation and storage projects that entered the portal from August 2020 and have been decided, half took 34 months or less.
Decided, 42 months
- $1.2bn
- Capital investment value
- 42 mo
- Time to decision Typical 34 mo
- 327
- Construction jobs
- StateState significant development, SSD-41020244
Approved. NSW Department of Planning. Lodged 12 April 2022. Decided 15 October 2025.
View record
Constraints
Public maps, asked when this page opens · within 5 kmChecking national and NSW maps…
Facts and sources
- Location
- 420 Avenue Road, Myrtle Creek NSW 2469, Richmond Valley, New South Wales
- Contractors
- Not named in a public source yet
- Value
- $1.2bn, capital investment value
- Jobs
- 327 during construction, 15 once operating
- Last activity
- 15 October 2025
- NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
- NSW Major Projects documentsCapital investment value stated in the Department's notice of decision, given as an approximate figure. Document: SSD Notice of Decisionn.pdf. Licence: CC BY 4.0. Retrieved 22 October 2026.
Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.