Data centres · Victoria
- To a 132 kV line
- <0.1 km
Overview
- Location
- Victoria-37.6450, 145.0820
- Value
- Not published
- Approving authority
- Australian Government (DCCEEW)
- Distance to the grid
- Under 0.1 km to a 500 kV line. 0.3 km to South Morang substation (500 kV).Straight line to operational lines and substations of 132 kV or more.
Approval progress
- PlanningNow
- Assessment
- Approved
- Construction
- Operating
The EPBC referral is the one instrument on record for this project. Later steps appear here as the public registers record them.
- EPBC Act referralCommonwealth · Australian Government (DCCEEW) · EPBC 2026/10668Referred, decision pending↗
Reports on this project
- Project brief, free.
- Project dossier, On enquiry.
- Insights report, On enquiry.
The facts on this page stay free.
What each contains© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the mapSite constraints
Site constraints
Checking national and VIC maps…
Nearby
- Findon Road Extension, South MorangApproved0.2 km
- Mernda Rail Extension Project, VicApproved3 km
- Boral Wollert Quarry ExpansionIn assessment3 km
- Yan Yean Road Stage 2 Upgrade, VicApproved5 km
- Northern Hospital RedevelopmentUnder construction · $813m6 km
- Staged redevelopment of 215 and 325C Cooper Street, Epping, VictoriaApproved6 km
Sources
- EPBC Act referrals, Australian GovernmentLicence: CC BY 4.0. Retrieved 22 November 2026.
- Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
Spotted an error? Tell us.
Get every change to data centres projects in VIC, and the firms you follow, in the Monday briefing.