Skip to content
In planningEPBC 2026/10668 · EPBC referred, decision pending

Proposed commercial construction of a data centre

Data centres · Victoria

To a 132 kV line
<0.1 km

Overview

Last activity 2026
Location
Victoria-37.6450, 145.0820
Value
Not published
Approving authority
Australian Government (DCCEEW)
Distance to the grid
Under 0.1 km to a 500 kV line. 0.3 km to South Morang substation (500 kV).Straight line to operational lines and substations of 132 kV or more.

Approval progress

1 approval on record
  1. PlanningNow

The EPBC referral is the one instrument on record for this project. Later steps appear here as the public registers record them.

  • EPBC Act referralCommonwealth · Australian Government (DCCEEW) · EPBC 2026/10668
    Referred, decision pending↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and VIC maps…
  1. Findon Road Extension, South MorangApproved0.2 km
  2. Mernda Rail Extension Project, VicApproved3 km
  3. Boral Wollert Quarry ExpansionIn assessment3 km
  4. Yan Yean Road Stage 2 Upgrade, VicApproved5 km
  5. Northern Hospital RedevelopmentUnder construction · $813m6 km
  6. Staged redevelopment of 215 and 325C Cooper Street, Epping, VictoriaApproved6 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. EPBC Act referrals, Australian GovernmentLicence: CC BY 4.0. Retrieved 22 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Spotted an error? Tell us.

Get every change to data centres projects in VIC, and the firms you follow, in the Monday briefing.