Wind · Energy

Pottinger Wind Farm

West Burrabogie Road · Edward River · New South Wales

ApprovedSSD-59235464No EPBC referral
-34.8482, 145.0300Open the map
© OpenStreetMap · OpenMapTiles · OpenFreeMap

Where the approval stands

How this is worked out

Decided 26 months after its first record on the NSW portal. Of the 63 NSW generation and storage projects that entered the portal from August 2020 and have been decided, half took 34 months or less.

Decided, 26 months
Half of 63 comparable cases decided by Apr 2026
$2.1bn
Estimated development cost
82
Conditions of consent
Counted from its numbering
26 mo
Time to decision
Typical 34 mo
  • StateState significant development, SSD-59235464

    Approved. Independent Planning Commission. Lodged 14 June 2023. Decided 30 July 2025.

    View record

Constraints

Public maps, asked when this page opens · within 5 km

Checking national and NSW maps…

Facts and sources

Location
West Burrabogie Road, Edward River, New South Wales
Owner
Not published
Contractors
Not named in a public source yet
Value
$2.1bn, estimated development cost
Conditions of consent
About 82, counted from the conditions of consent on the NSW Major Projects portalCounted from the document's condition numbering, not read one by one.
Last activity
30 July 2025
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 22 October 2026.
  2. NSW Major Projects documentsEstimated development cost stated by the applicant in the application form. Document: Application_20240523043426.pdf. Retrieved 22 October 2026.

Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.