Skip to content
WithdrawnSSD-35922866 · No EPBC referral

Norwest High School

Education · 3 Brookhollow Ave, Norwest · The Hills Shire · New South Wales

To a 132 kV line
0.2 km

Overview

Last activity 31 January 2022
Location
3 Brookhollow Ave, Norwest, The Hills Shire, New South Wales-33.7320, 150.9680
Value
Not published
Approving authority
NSW Department of Planning
Distance to the grid
0.2 km to a 132 kV line. 7.1 km to 330 kV. 1 km to West Castle Hill substation (132 kV).Straight line to operational lines and substations of 132 kV or more.
NSW portal case
SSD-35922866First record 31 January 2022

Approval progress

1 approval on record
  1. Planning
  2. AssessmentLodged 31 Jan 2022
  3. WithdrawnDate not published
  • State significant developmentNew South Wales · NSW Department of Planning · SSD-35922866
    31 Jan 2022 → date not published
    Withdrawn↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and NSW maps…

Comparable projects

Education projects in New South Wales. Grey is the middle half of them, the marker is this project.
  • Modifications77 comparable projectsNone1.8 on average, half have 2 or fewer

Time to decision comes from the approval times benchmark. Condition counts are read from each consent's numbering.

  1. Mixed-use development at 32 Brookhollow Avenue, NorwestIn planning · $68m0.6 km
  2. Century Hills - Hills CLCIn planning · $1.1bn0.8 km
  3. 40 Memorial Ave, Bella Vista - residential towersApproved3 km
  4. Samantha Riley Drive - Mixed use developmentIn assessment · $360m4 km
  5. BaptistCare Aminya VillageIn planning4 km
  6. Mixed Use Redevelopment and Rezoning at Warringah MallIn planning5 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.
  3. NSW Major Projects, case recordDetermination authority, portal stage and modification cases. Licence: CC BY 4.0. © State of New South Wales and Department of Planning, Housing and Infrastructure.

Spotted an error? Tell us.

Get every change to education projects in NSW, and the firms you follow, in the Monday briefing.