Energy · Electricity generation - Other

Newcastle Power Station

Approved
Location
<p>1940 Pacific Highway, Tomago</p>, Port Stephens, New South Wales
Value
$439m, capital investment value
Jobs
300 during construction, 23 once operating
Owner
Not published
Contractors
Not named in a public source yet
State approval
Approved
Federal approval (EPBC)
No EPBC referral matched
Last activity
14 March 2021
See it on the map

Approvals

  • StateState significant infrastructure, SSI-9837

    Approved. Minister for Planning. Lodged 27 February 2019. Decided 14 March 2021.

    View record

Nearby projects

Sources

  1. NSW Major Projects documentsCapital investment value stated in the Department's assessment report. Document: Newcastle Power Station - Assessment Report.pdf. Licence: CC BY 4.0. Retrieved 21 October 2026.
  2. NSW Major Projects portalLicence: CC BY 4.0. Retrieved 20 October 2026.

Facts on this page come from the public records above. How the Pipeline is built. Spotted an error? Tell us.