Skip to content
ApprovedNo EPBC referral

New Acland Coal Mine Stage 3

Mining · Queensland

To a 132 kV line
38 km

Overview

Expansion of the existing New Acland open-cut coal mine, from 4.8 million tonnes per annum (Mtpa) to up to 7.5 Mtpa.

Location
Queensland-27.3111, 151.6962
Value
Not published
Approving authority
Queensland Coordinator-General
Distance to the grid
38 km to a 275 kV line. 43 km to Middle Ridge substation (330 kV).Straight line to operational lines and substations of 132 kV or more.

Approval progress

1 approval on record
  1. Planning
  2. Assessment
  3. ApprovedNow

Coordinated project is the one instrument on record for this project. Later steps appear here as the public registers record them.

  • Coordinated project, environmental impact statementQueensland · Queensland Coordinator-General
    Assessment completed↗

Reports on this project

  • Project brief, free.
  • Project dossier, On enquiry.
  • Insights report, On enquiry.

The facts on this page stay free.

What each contains
© OpenStreetMap · OpenMapTiles · OpenFreeMap
Open in the map

Site constraints

Public maps asked live, on the site and within 5 km · How it works

Site constraints

Public maps, checked as this page opens · within 5 km
Checking national and QLD maps…
  1. Oakey Solar Farm, Warrego Highway, Oakey, QueenslandApproved12 km
  2. Wetalla Water PipelineApproved14 km
  3. Inland Rail Gowrie to Helidon Project, QldIn assessment36 km
  4. Jubilee and Prince Henry Drive Park Mountain Bike TrailsIn assessment40 km
  5. Cressbrook Dam improvementUnder construction · $54m51 km
  6. Big-T Pumped Hydropower Energy Storage ProjectIn assessment53 km

Sources

Every fact links to the public record it came from · How the Pipeline is built
  1. Coordinated projects, the Coordinator-GeneralDeclared a coordinated project under the State Development and Public Works Organisation Act 1971: completed eis, the Coordinator-General's evaluation report issued. The location is the indicative project area published by the Coordinator-General. © State of Queensland. Licence: CC BY 3.0 AU. Retrieved 22 November 2026.
  2. Geoscience Australia, Electricity InfrastructureDistance to the grid, measured by claused. from the project's mapped point. Licence: CC BY 4.0.

Spotted an error? Tell us.

Get every change to mining projects in QLD, and the firms you follow, in the Monday briefing.